The Ambedkar Bhavan on Dewan’s Road in central Mysuru is expected to be ready in two months, more than 14 years after the project began, according to officials of the Mysuru Development Authority (MDA). The project is now reported to be about 80% complete.
The building was sanctioned by the State government on May 4, 2012, at an estimated cost of Rs 14.66 crore. Construction began on an 80×80-foot plot, with civil work covering about 6,000 square feet. Work was halted in 2020 after the civil works were completed, with officials citing a shortage of funds.
By June 22, 2020, around Rs 20.66 crore had been spent on the project. This included Rs 10.65 crore from the erstwhile Mysuru Urban Development Authority, now known as the MDA, Rs 3 crore from Mysuru City Corporation, Rs 50 lakh from Mysuru Zilla Panchayat and Rs 6.50 crore from the Social Welfare department, according to the report.
The incomplete building then required a fresh funding and estimation process. The Social Welfare department submitted a revised estimate of Rs 22.3 crore to the government in March 2023 for completing the project. The Cabinet approved the work at a cost of Rs 19.1 crore around December 2023 or January 2024 and directed the urban development authority to fund it. The authority later submitted another estimate seeking approval for Rs 27 crore.
The MDA ultimately allotted Rs 23.84 crore for the remaining works in its 2025-26 budget. These works include seating for about 1,700 people, two green rooms, two VIP rooms, a stage, water supply, toilets, an underground drainage system, false ceilings, electrification, air-conditioning, interior design, acoustics, a sound system and wall paneling.
The project also includes development of the road within the premises, a fountain and other site facilities. Provision for rainwater harvesting is being made in the building, Assistant Engineer Nadeem of MDA Zone 4 said, according to the report. A statue of Dr B R Ambedkar has been installed in front of the structure.
District In-charge Minister S Yathindra inspected the building with Dalit leaders on Friday evening and directed officials to complete the work within the stipulated period while maintaining construction quality. He said the facility would support events organised not only by Dalit communities but also by other groups.
The project’s history highlights the implementation risks surrounding publicly funded civic buildings. The initial approval, expenditure on civil works, stoppage caused by funding constraints and multiple revised estimates have extended delivery well beyond the original project start. The latest two-month completion target therefore remains dependent on the remaining works being finished as scheduled and on the quality checks directed by the minister.
Once completed, the auditorium is intended to provide a large public venue in the heart of Mysuru, with event infrastructure, visitor facilities and water-management provisions. The report does not state the precise date on which the building will open to the public.