Yadadri Power Plant Nears Full Capacity With Fifth Unit Set for December

The Yadadri Thermal Power Station in Telangana is set to reach its full installed capacity of 4,000 MW after the fifth 800 MW unit is expected to begin commercial operations in December, strengthening the state’s domestically generated electricity supply ahead of the Rabi crop season.

Four of the five units at the plant in Damaracherla mandal of Nalgonda district are already producing power. The fifth unit was synchronised with the grid on October 20, marking a key step towards commissioning the entire station.

Telangana Power Generation Corporation Limited (TGGENCO) is implementing an action plan to resolve technical issues in the plant’s coal-handling system and support uninterrupted generation from all five units. According to TGGENCO officials, the plant’s major generation and ancillary systems, including the boiler, turbine, generator, ash-handling system and water-supply network, are functioning satisfactorily.

The coal-handling plant had reported technical problems that affected the regular movement of fuel to the units. Following on-site inspections, a high-level team comprising officials from Bharat Heavy Electricals Limited (BHEL) and TGGENCO formulated measures to restore the system. The team was led by Energy Department Special Chief Secretary Vikas Raj and included TGGENCO chairman and managing director Dr S. Harish.

Four coal-feeding lines have since been restored. Each line can supply an average of 800 tonnes of coal per hour, taking the plant’s coal-handling capacity to 3,200 tonnes per hour, according to the report. The restoration has reduced interruptions in coal supply and improved the plant’s operating performance.

The state has also arranged for three to four coal rakes to be transported daily from Singareni Collieries Company Limited’s Naini coal mine. A total of 4.26 lakh metric tonnes of coal has so far been transported from Naini to Yadadri. Agreements have also been finalised for the procurement of 4.6 lakh tonnes of coal from Mahanadi Coalfields Limited and South Eastern Coalfields Limited through the Window-II auction mechanism. Fuel Supply Agreements with the companies were concluded on November 4, and transportation has begun.

A longer-term coal arrangement has also been approved. The Standing Linkage Committee has cleared the annual supply of 7.71 million metric tonnes of coal from Mahanadi Coalfields Limited and Eastern Coalfields Limited, both subsidiaries of Coal India Limited, for two units of the Yadadri plant. The arrangement is intended to address concerns related to coal availability and quality.

The project faced delays linked to the Covid-19 pandemic, forest clearances, railway land-related issues and directions from the National Green Tribunal concerning environmental permissions. Environmental Impact Assessment studies and public hearings were completed afresh, while construction activities resumed in February 2024.

The plant’s contribution to Telangana’s grid has increased as more units became operational. On November 11, the state recorded power generation of 6,088 MW, described in the report as an all-time high in Telangana’s power-generation history. Yadadri alone generated 2,754 MW on that day.

The fifth unit’s expected commercial commissioning in December will determine whether the station can move from partial operation to full-scale generation across all five units. TGGENCO’s coal-handling measures and supply arrangements remain central to that transition.