Nashik-Trimbakeshwar Road Upgrade Reaches 16 Km Ahead of Kumbh

The Nashik-Trimbakeshwar road six-laning project has reached a key milestone, with one side of a 16-kilometre stretch completed as a three-lane cement-concrete carriageway ahead of the 2027 Simhastha Kumbh Mela. The remaining side is being prepared after the top layer of the existing asphalt road was removed.

The 28-kilometre highway connects Nashik and Trimbakeshwar, two important pilgrimage centres, and is being widened from four lanes to six lanes as part of the infrastructure preparation for the Kumbh Mela. The Public Works Department is responsible for a 17-kilometre section of the route, while the remaining stretch falls under the Nashik Municipal Corporation.

According to the report, work on one side of nearly the entire 17-kilometre section under the Public Works Department is expected to be completed shortly. Construction on the other side is continuing, with excavation and surface preparation under way before the concrete pavement is laid.

The project is being executed against an estimate that around 12 crore devotees could visit Nashik and Trimbakeshwar during the 2027 Simhastha Kumbh Mela. The road expansion is among a wider set of infrastructure works undertaken by the government for the event, for which all planned works have been given a March 2027 completion deadline.

The construction has, however, created difficult travel conditions on the route. Traffic has been operating in both directions on one side of the road for several months, while diversions, excavation, pothole-ridden asphalt, dust and congestion have affected movement between Nashik and Trimbakeshwar. The urban section of the route has also faced similar disruption.

The road has also recorded several small and major accidents since construction began, according to the report. Vehicle users have faced delays while navigating congestion and work zones, and the condition of the road has required authorities to carry out repairs and patchwork ahead of high-profile travel linked to a flag-hoisting ceremony.

The division of responsibility between the Public Works Department and the Nashik Municipal Corporation means that the full 28-kilometre corridor depends on coordination between two implementing agencies. While the department-controlled section is nearing completion on one side, the report does not provide a specific date for when the entire route will be opened to traffic.

The next major deadline is March 2027, when the government expects the Simhastha-related infrastructure works to be completed. Until then, commuters and pilgrims using the Nashik-Trimbakeshwar corridor will continue to depend on traffic diversions and partially completed carriageways as construction progresses.