HomeAnalysisVaranasi Airport Expansion Links New Terminal to NH 56 Upgrade

Varanasi Airport Expansion Links New Terminal to NH 56 Upgrade

Varanasi airport expansion work is linking a larger passenger terminal with a road underpass beneath the runway, creating a combined infrastructure programme intended to increase air capacity while retaining the NH 56 connection near Babatpur. A site review on November 20 found that construction of the new terminal was about 71% complete and the runway underpass about 60% complete, according to a report by MagicBricks.

The review was conducted at Lal Bahadur Shastri International Airport by Divisional Commissioner K. Vijayendra Pandian. Department officials presented progress reports on the terminal and the flyover-underpass works, while the commissioner asked implementing agencies and the Airports Authority of India (AAI) to maintain construction quality and meet the scheduled timelines.

The airport development programme was approved by the Union Cabinet on June 19, 2024, at an estimated cost of Rs 2,869.65 crore. The plan is intended to raise the airport’s annual passenger-handling capacity from 39 lakh to 99 lakh. The proposed terminal is designed to handle 60 lakh passengers a year and 5,000 passengers during peak hours.

The new passenger terminal is planned over approximately 75,000 square metres. The approved scope includes additional check-in facilities, eight proposed aerobridges, a new apron with parking capacity for 20 aircraft, multi-level vehicle parking and an elevated road to improve access to the departure area. The building is also described as incorporating design references to Varanasi’s heritage.

Officials told the commissioner that the terminal has a July 2027 completion target. The project’s scale means that passenger processing, aircraft parking, vehicle access and landside circulation will be reorganised together rather than through a terminal-only expansion. However, the report does not provide a detailed phasing plan for how existing airport operations will be managed during the remaining construction period.

The associated road project is a 2.89-kilometre underpass along the Varanasi-Lucknow highway corridor, identified in the report as NH 56. It is intended to allow road traffic to pass beneath the airport runway. This arrangement would make room for the planned runway extension while preserving the road connection between the airport area and the wider highway network.

The underpass has an estimated cost of Rs 649.44 crore and a March 2027 completion target. With around 60% of the work reported complete at the November 20 review, the remaining construction will determine whether the runway and highway works can be brought into coordinated operation. The source report does not specify the number of traffic lanes, junction changes, diversions or pedestrian facilities planned for the underpass.

Airfield works under the approved programme include extending the runway to 4,075 metres by 45 metres, adding a parallel taxiway and constructing the new aircraft apron. These elements are intended to support higher aircraft-handling capacity alongside the terminal expansion. The plan also lists solar power, energy optimisation, waste recycling, lower carbon emissions and greater use of natural daylight as proposed environmental features.

The airport’s expansion has wider implications for the northern edge of Varanasi because its road access and airside capacity are being upgraded at the same time. Areas along the Babatpur and airport-road belt, the Harahua-NH 56 corridor and parts of Pindra tehsil are identified in the report as locations where buyers are watching connectivity and land records. Such interest does not, by itself, establish that property values will rise, and the report provides no independent transaction data or official land-use assessment.

For residents and road users, the immediate public-interest issue is the relationship between construction activity and continuity of movement on the highway corridor. A runway underpass can separate airport operations from through traffic, but its effectiveness will depend on approaches, junction design, drainage, lighting, maintenance and safe access for people travelling to nearby settlements. None of these operational details is set out in the source report.

The November review therefore places the focus on delivery discipline as much as on the final infrastructure. The terminal, runway, taxiway, apron, parking facilities, elevated access road and underpass form an interdependent programme. Delays or changes in one element could affect how the expanded airport connects with the surrounding road network. The next stated milestones are the March 2027 target for the NH 56 underpass and the July 2027 target for the new terminal.