TGRERA Orders Refunds and Repairs Across 17 Projects

TGRERA orders against 17 real estate developers in Telangana have directed refunds to homebuyers, registration of allotted plots, removal of mortgage-related encumbrances, delivery of promised parking and completion of essential infrastructure works, according to a report by Deccan Chronicle.

The cases covered residential layouts, apartment projects, villa developments and commercial properties. The complaints involved delayed registrations, unregistered projects, dishonoured refund cheques, incomplete amenities and other alleged violations of obligations under the Real Estate (Regulation and Development) Act, 2016.

The orders show how disputes in Telangana’s property market can extend beyond possession and refunds to basic questions of land title, layout approval and the delivery of services promised to residents and plot buyers.

In one matter, the Telangana Real Estate Regulatory Authority upheld the claims of 38 members of the Elite BHEL Employees Housing Society. It directed the concerned landowner-promoter to execute and register sale deeds for their allotted plots after receiving the outstanding sale consideration.

In the Jaswitha Estates project at Shankarpally, Sand Stone Infra was directed to refund ₹47 lakh. BVR Infra Developers was ordered to refund ₹6.10 lakh, along with annual interest of 10.85 per cent, to a purchaser of Plot No. 91 in SV Electronic City-3.

A separate case involving BVR Infra’s SV Golden City-V project at Ramanuthala resulted in directions to obtain final layout approval, clear encumbrances on Plot No. 97, measuring 212 square yards, and complete registration of the plot in favour of the purchaser.

In the Googee Satellite Township project at Nomula, Googee Properties was directed to refund ₹18.80 lakh to a purchaser within 60 days. Nest Infra Developers was ordered to return a ₹1 lakh booking amount within 15 days in the Rayan Enclave case at Bibinagar.

The Authority also imposed a penalty of ₹57,735 in a case concerning an unregistered plotted layout at Gurralapadu in Khammam. In the Signature Towers case at Thumkunta, Ashritha’s Group was directed to refund ₹9 lakh collected towards a flat booking within 60 days.

For the Sudheesha Dimple Valley project at Puppalaguda, Sudheesha Constructions was directed to refund ₹10 lakh with annual interest of 10.85 per cent and pay a penalty of ₹8,24,585. In the Kapil Business Park matter, involving Kausalya Infra Projects and BVM Energy & Residency, the complainant was allowed to withdraw from the commercial unit allotment. The developers were directed to refund ₹24,64,259 within 60 days, without interest.

Several orders dealt with facilities that directly affect the usability of completed or occupied developments. Sree Builders was directed to allot and hand over two cellar parking spaces at the Sree Towers project in Gajularamaram. Honer Developers was ordered to provide one car parking space to complainants at Honer Aquantis in Gopanpally within 60 days, in coordination with the Flat Owners’ Association.

At the Ayyappa Sri Rasthu project in Siddipet, Ayyappa Builders was directed to rectify deficiencies in essential amenities. The required work included constructing a proper septic tank, completing drainage pipelines and providing generator backup for both blocks. The Authority gave the developer 60 days to complete the work at its own expense.

The regulator also warned RSR Greenway Infra not to advertise, market, book or sell villas or other units in the Rocketry Villa Project at Pocharam without mandatory RERA registration. The report said the developer had collected ₹95.10 lakh from complainants towards a villa without securing the necessary approvals.

In an execution petition concerning RDB Hyderabad Infrastructures’ RDB Coconut Grove Apartment, TGRERA imposed a continuing penalty of ₹5.34 lakh. In contrast, the Authority dismissed a refund claim in the Parijatha Homes case, observing that the complainant continued to hold legal ownership of the plot under a registered sale deed and could not seek a refund while retaining ownership.

Taken together, the reported orders underline the range of remedies available in disputes involving property transactions: repayment, interest, penalties, registration, removal of encumbrances, delivery of common facilities and correction of basic project infrastructure. They also indicate that buyer grievances can involve both financial loss and the inability to secure legally usable, serviced or properly documented property.

The individual directions remain tied to the facts and orders in each case. Their practical effect will depend on compliance by the concerned developers and on the execution of the Authority’s directions within the periods specified in the reported orders.