The Shahberi double-decker road project in Greater Noida has moved closer to implementation after the Greater Noida Authority wrote to the National Highways Authority of India (NHAI), seeking progress on the proposed elevated corridor intended to ease congestion between Greater Noida West and Ghaziabad.
The project is planned as Uttar Pradesh’s first double-decker elevated road, according to the report. The Greater Noida Authority’s letter is expected to accelerate preparation of the detailed project report and other preliminary work. NHAI is expected to take up the next stage of the project.
Greater Noida Authority CEO Ravi Kumar NG said the elevated road would begin at Ek Murti roundabout and continue up to Shahberi drain as a two-level structure. Beyond the drain, the plan provides for a single-level elevated road. The project is estimated to cost around Rs 1,200 crore.
Under the current proposal, the corridor will include a 130-metre-wide road in Greater Noida West that will pass through Shahberi and Crossings Republik before connecting with National Highway 9. The planned elevated section is about 2.5 kilometres long. It is proposed as a three-lane double-decker road, with one level carrying vehicles from Greater Noida towards Ghaziabad and the other carrying traffic from Ghaziabad towards Greater Noida.
The existing road is expected to remain open after construction of the elevated structure. The elevated road is estimated to be 9 to 10 metres wide. The plan also includes another road along the Shahberi drain, connecting near Tigri with an existing 60-metre-wide road.
The project has been prepared jointly by the Greater Noida Authority, the Noida Authority, the Ghaziabad Development Authority and NHAI. The construction cost is to be shared by the Noida, Greater Noida and Ghaziabad development authorities, according to the report.
The proposal has changed substantially from an earlier plan for a four-lane elevated road at Shahberi. Officials from the Greater Noida Authority and NHAI discussed that option last month, with the assistance of a consultant. The four-lane project had been estimated to cost around Rs 400 crore. The authorities subsequently moved towards a double-decker design, raising the estimated cost to approximately Rs 1,200 crore.
The corridor is intended to provide an additional east-west connection for residents and commuters using the rapidly developing Greater Noida West area. Its proposed alignment also links jurisdictions administered by different development authorities, making coordination over design, funding, land and construction a central part of the project’s implementation.
The Greater Noida Authority’s letter to NHAI marks the latest reported step in moving the project from planning towards detailed design and execution. Further progress will depend on preparation of the detailed project report and the subsequent decisions of the participating authorities.