Ranchi-Bokaro Highway Nears 90% Completion, Travel Time Set to Fall

The 60-km Ranchi-Bokaro highway corridor is nearing completion, with about 90% of the four-laning work finished, according to National Highways Authority of India officials. The Ormanjhi-Gola-Jaina More route is expected to reduce the journey between Ranchi and Bokaro from about 2.5 hours to nearly one hour and 15 minutes once it opens.

The Rs 2,224-crore project is being developed under the Bharatmala Pariyojana and is intended to improve road connectivity between Ranchi and the Bokaro-Dhanbad industrial belt. It is also linked to the proposed Raipur-Dhanbad Economic Corridor. The new corridor is expected to ease traffic pressure on the existing Chas-Ramgarh route.

The project is divided into two NHAI packages. The 27.85-km Ormanjhi-Gola section forms part of NH-320B, while the 32.49-km Gola-Jaina More section forms part of NH-320. The alignment begins on the Ormanjhi side in Ranchi district, passes through Gola and Dulmi in Ramgarh district, and ends at Jaina More in Bokaro district.

Government project documents put the design length at approximately 60.34 km, while the originally sanctioned stretch was cited as 59.94 km. The corridor is being built through an area where the existing road via the Sikidiri valley has been associated with frequent accidents and passes through an elephant corridor.

NHAI officials said five wildlife passages had been incorporated into the project. These include three underpasses and a flyover intended to support animal movement across the highway. Ramgarh divisional forest officer Nitish Kumar had earlier said the size of the crossings, particularly those meant for elephants, was an important safety and conservation concern.

Forest clearance documents show that the project involves forest land in the Ranchi-Ramgarh stretch. NHAI regional office official Vijay Kumar said special attention had been given to wildlife movement during construction through the Kulhi and Gola areas.

The project has also faced concerns over local access. Villagers near Kulhi Chowk in Dulmi demanded an entry point and an underpass, citing access and safety requirements. Giridih MP Chandra Prakash Choudhary inspected the site and raised concerns related to the demands.

The corridor’s next milestone is the completion of the remaining construction work before the four-lane route is opened for traffic. Its final operational benefits will depend on the completion of the planned highway infrastructure, wildlife crossings and local-access arrangements.