HomeAnalysisPune Timber Market Fire Raises Questions Over Emergency Access

Pune Timber Market Fire Raises Questions Over Emergency Access

A fire at Pune’s Timber Market in Bhawani Peth has prompted councillors to demand the removal of alleged encroachments and action over a delayed culvert project, which they said obstructed fire brigade access to the site.

The issue was raised during the Pune Municipal Corporation’s general body meeting on Wednesday, following the early-morning fire at the market. Local councillors alleged that unauthorised shops had expanded over municipal land in the area over several years. They said the encroachments affected lawful businesses and also made it harder for emergency vehicles to reach the fire site.

Councillor Ajay Khedekar said an unauthorised shop was damaged in the fire and called for all encroachments to be removed. He also proposed developing a garden on the municipal land after its clearance.

Khedekar further alleged that work on a culvert over a stream near Chandan Sweet Mart had been delayed for about 14 months. According to him, the incomplete work created an obstruction for fire brigade vehicles, resulting in a delay even while covering a distance of about 100 metres.

The alleged obstruction has wider implications for emergency access in a dense commercial area, where unauthorised structures and incomplete civil works can restrict vehicle movement. However, the claims about the role of the encroachments and culvert in delaying firefighting operations were made by councillors during the municipal meeting and have not been independently documented in the report.

Councillors Ganesh Kalyankar, Aishwarya Thorat and Mrinal Kamble supported the demand for strict action against the contractor responsible for the culvert work. They called for the contractor to be blacklisted for failing to complete the project on time.

Mayor Manjusha Nagpure directed that the incident be investigated and that a report be placed before the general body. The councillors’ demand for immediate action against the contractor was not accepted by municipal commissioner Naval Kishore Ram.

Ram said the contractual deadline for the culvert work was April 2027 and that action could not currently be taken against the contractor solely on the basis of the incident. He said it would not be appropriate to act against anyone in response to immediate emotions, and that the administration would submit a report after investigating the matter. The general body could then take an appropriate decision, he said.

The inquiry is expected to determine the condition of access routes during the fire, the status of the encroachments on municipal land and whether the culvert work caused a documented delay in emergency response. The report does not specify a date for submitting the findings.