Two stations on Pune’s 23.3-kilometre Hinjewadi-Shivajinagar metro corridor could open to commuters in December, subject to inspection and clearance by the Commissioner of Metro Railway Safety (CMRS), according to senior Pune Metropolitan Region Development Authority (PMRDA) officials.
The Baner Gaon station, identified as PMR-15, and the Baner-Pashan Link Road station, identified as PMR-16, have completed construction. Pre-safety inspection procedures are under way, with a CMRS team expected to inspect the route this week.
Passenger services can begin only after the stations receive the required safety clearance. If the inspection identifies deficiencies, the concessionaire could need another 10 to 12 days to address them before the compliance process is completed, according to the report.
If the inspection and follow-up work remain on schedule, the two stations would increase the number of operational stations on the corridor from 17 to 19. PMRDA aims to make the full corridor operational by January 2027, with the remaining four stations scheduled to open in phases by then. That would take the total number of operational stations on the route to 23.
The proposed openings also highlight the need for better station-access infrastructure, particularly parking. PMRDA has sought eight plots from the Pune Municipal Corporation (PMC) to develop parking facilities, with most of the proposed sites located in Baner and Balewadi.
The PMC has submitted conditions and compensation options for transferring the land to PMRDA, and further proceedings are under way. According to PMC data cited in the report, only 31 of the 137 plots reserved for public parking have been developed. Parking facilities have also been created at only five of the 20 sites identified for parking near metro stations.
In the absence of adequate parking, commuters often leave vehicles along roadsides and beneath metro corridors, contributing to traffic congestion. The report said that parking facilities near stations are expected to discourage private vehicle use and support greater reliance on public transport.
The December target therefore remains dependent on two linked processes: completion of the CMRS safety-clearance procedure for the stations and progress on land and parking arrangements around the expanding metro network.