Palakkad’s Nadakkavu railway overbridge at Akathethara is scheduled to open on December 11, offering an alternative to a railway level crossing that residents say caused prolonged delays for road users and disrupted access to emergency medical care.
The opening date was announced by V.K. Sreekandan, Member of Parliament, and A. Prabhakaran, Member of the Legislative Assembly, according to Malayala Manorama. V.D. Satheesan is scheduled to inaugurate the bridge at an evening event, the report said.
The bridge was built at a cost of Rs 54 crore through funding allocated by the Kerala Infrastructure Investment Fund Board (KIIFB), with the project financed entirely through state government funds, according to the report.
The project’s foundation stone was laid in 2017 by former Kerala Chief Minister V.S. Achuthanandan. Construction was formally launched in 2021 by then Chief Minister Pinarayi Vijayan. The bridge has now been completed in the ninth year after the initial foundation-stone ceremony.
The opening had been planned around the Kalpathy Ratholsavam, but was delayed because the mandatory load-testing process took longer than expected. The report said the load test was successful and that the formal test report was expected on the following day.
The Nadakkavu railway gate is located close to Palakkad Junction railway station. According to the report, the gate was closed for more than nine hours a day, across several intervals, to allow trains to pass. Residents said the resulting delays affected emergency treatment and claimed that several people had died after medical access was hindered. These claims were reported by Malayala Manorama and were not independently documented in the source material.
Residents had campaigned for the overbridge for years and held protests, including a symbolic protest in mud, while also pursuing legal action over construction delays. Local representatives and the former and current administrations of Akathethara panchayat were reported to have intervened in the matter.
The bridge’s opening is expected to remove the need for vehicles to wait at the Nadakkavu railway gate, subject to the completion of the remaining formalities and the scheduled inauguration.