The Bilaspur flyover on the Delhi-Jaipur highway is expected to fully open to traffic by December 20, with bituminous surfacing under way on the Jaipur-bound carriageway, the National Highways Authority of India (NHAI) said on Friday.
NHAI said the Jaipur-bound carriageway is expected to open in the first week of December, while work on the Delhi-bound carriageway is nearing completion and is scheduled to finish by December 20. The authority said the flyover is in the final stages of construction and that bitumen is being laid on the road surface.
The update also covers works on the Gurugram-Pataudi-Rewari highway. NHAI plans to open the Rewari-bound carriageway of the Pahari railway overbridge by December 31. The four-lane overbridge is being built over the Pataudi-Rewari railway line near Pahari village.
According to the authority, the other carriageway of the Pahari overbridge is expected to be completed by March 2027. NHAI said about 95% of the Gurugram-Pataudi-Rewari highway project has been completed.
A separate flyover connecting the Dwarka Expressway with the highway towards Pataudi is also under construction. NHAI said the flyover and the entire highway project are expected to be completed by March 2027.
At Wazirpur, NHAI has secured permission from the Bhakra Beas Management Board to shift high-tension power lines. The authority said work would begin shortly, after which the Wazirpur flyover would be opened to traffic.
NHAI is also constructing a 16-lane toll plaza at Janaula village, which is expected to be completed by the end of December.
The 45-kilometre Gurugram-Pataudi-Rewari highway is being built at a cost of ₹1,900 crore, according to NHAI officials.