Nashik Phata–Khed Corridor Clears Key Land Hurdle

The National Highways Authority of India (NHAI) has completed land acquisition and documentary possession for the proposed 29.92-km Nashik Phata–Khed elevated corridor in Maharashtra’s Pune region, according to a report by Pune Mirror. The ₹7,827-crore project is now awaiting financial and contractual formalities before construction can begin.

The eight-lane corridor will run along the Pune–Nashik highway, or NH-60, linking traffic centres and industrial areas across Pimpri-Chinchwad, Bhosari, Moshi, Chakan and Rajgurunagar. Construction could start within six to eight weeks of the report, potentially around January 2027, but NHAI has not announced a formal commencement date.

The land acquisition involved the Pimpri-Chinchwad Municipal Corporation, Pune Metropolitan Region Development Authority and Maharashtra State Road Development Corporation. PCMC facilitated 3.869 hectares, PMRDA contributed 4.104 hectares and MSRDC facilitated 6.128 hectares, taking the reported total to 14.101 hectares.

The project’s Letter of Award was issued to the successful bidder on October 28, 2026. It is being developed under the Build-Operate-Transfer model and has a stipulated construction period of 36 months. March 2030 had previously been identified as the completion target.

The current design replaced an earlier proposal for a conventional six-lane highway with service roads, underpasses and flyovers. The original tender, floated in 2019–20, was cancelled after developments linked to the proposed Chakan Metro project. The revised elevated-corridor design required additional land, particularly for entry and exit ramps.

Alongside the elevated structure, the project includes widening of the existing highway to four or six lanes, two-lane service roads on both sides, nine major junctions, two major bridges and dedicated ramps. The stated objective is to separate long-distance traffic from local movement and ease congestion near Bhosari, Moshi, Kuruli, Chimbali and Chakan.

NHAI will also coordinate with Maha Metro to avoid technical conflicts with proposed metro infrastructure along the highway. Until the corridor becomes operational, upkeep of the existing route—including pothole repairs, drainage, lighting and traffic management—will remain important for daily commuters and commercial vehicles.