Nashik Municipal Corporation will begin large-scale asphalting of roads being prepared for the 2027 Simhastha Kumbh Mela after Diwali, with the civic body aiming to complete the work one to two months before the March 2027 deadline.
The Nashik Municipal Corporation has completed inspections of asphalt plants operated by contractors involved in the project, including checks on bitumen and other construction materials, officials told the Times of India. The civic body has also made arrangements with public-sector petroleum companies to ensure bitumen is supplied within two days of an order being placed.
NMC commissioner Manisha Khatri said the corporation was ready to begin the road works after the festival. “We have inspected the asphalt plants of the contractors and checked the quality of bitumen and other materials. We will start the Kumbh road asphalting works after Diwali,” she said. Khatri added that although the formal completion deadline was March 2027, the corporation was targeting completion around one to two months earlier.
The road programme covers nearly 32 roads spanning about 150 km across Nashik, at an estimated cost of Rs 1,400 crore. Around 40% of the network will be built using cement concrete, while the remaining stretches will be bituminous roads requiring extensive asphalting. The works also include road widening wherever there is scope, according to an NMC official.
The asphalting schedule had been affected by a shortage of bitumen in May and June. Officials attributed the disruption to geopolitical tensions in West Asia. The monsoon caused a further delay because large-scale bituminous road works could not be carried out during the rains. With the monsoon almost over, the civic body now plans to take up the asphalt works across the identified stretches.
The NMC has completed the tender process for 30 road projects, and work has started on several stretches. Construction of cement concrete roads is also progressing at multiple locations. Officials said most of these works are expected to be completed by December-end, while the remaining projects are scheduled for completion by March 2027.
Completing the major works ahead of the deadline would give the civic body additional time for finishing touches and other related preparations before the large religious congregation. The immediate milestones are the post-Diwali start of large-scale asphalting and the continued execution of the cement concrete road projects.