The National Highways Authority of India (NHAI) has extended the bid-opening date for the first construction package of the proposed Mumbai–Pune Greenfield Expressway to November 27, 2026, according to the revised tender schedule reported by Pune Mirror. Bidders can submit proposals until November 26, with bids scheduled to open at 11.30 am the following day.
The change concerns the 29.219-km Pagote–Chowk section, planned as a six-lane greenfield highway linking the JNPT-side road network with the existing highway corridor near Chowk. The section is expected to include two tunnels through the Sahyadri ranges and has an estimated tender value of about ₹3,653 crore.
The package will be developed under the Build-Operate-Transfer (Toll) model, with a construction period of 910 days specified in the tender. It is the first section of the larger proposed corridor, which is approximately 130 km long and estimated to cost around ₹15,000 crore.
The wider project is being planned as an alternative route to the existing Mumbai–Pune Expressway. Its proposed alignment would connect the Mumbai metropolitan region, the JNPT and Navi Mumbai area, and the Pune-side highway network. The remaining stretch is planned from Chowk towards Shivare village near Bhor, where it is expected to connect with the Pune Ring Road. That section is approximately 100 km long and remains under wider project planning.
The proposed expressway is intended to add capacity for passenger and freight traffic, with a projected journey time of about 90 minutes between Mumbai and Pune once the full corridor is completed. However, the tender deadline extension does not mean that construction has started. Bid evaluation, contractor selection, land-related processes and other approvals will determine the next stages. No confirmed completion or opening date for the full expressway has been announced.