Mumbai Consumer Order Secures Goregaon Flat Handover, Interest

The Maharashtra State Consumer Disputes Redressal Commission has directed Raj Builders & Developers to hand over a 351 sq ft carpet-area flat in its Raj Pantheon project at Goregaon West within two months, along with the Occupation Certificate (OC), according to a report by the Free Press Journal.

The Commission also ordered the developer to pay the buyers 9 per cent annual interest on the amount paid towards the flat from January 1, 2023, until actual possession. It awarded ₹2 lakh as compensation for mental agony and harassment, besides ₹50,000 towards litigation costs.

The flat, located on the 18th floor of the project’s A-Wing, was booked by a couple in October 2018 for ₹73 lakh. The developer had initially assured them that construction would be completed and the OC obtained by December 31, 2021.

According to the complaint, the buyers paid ₹14.78 lakh between October 2018 and October 2019. They alleged that the developer did not execute a registered Agreement for Sale for more than three years, despite receiving over 20 per cent of the flat’s consideration.

The buyers also contested interest demands of ₹10.81 lakh raised at 21 per cent annually. The developer later admitted that the earlier demands were faulty and withdrew them, but similar demands were raised again in 2023, the report said.

By the time the complaint was filed, the buyers stated that they had paid ₹64.80 lakh, or about 90.5 per cent of the total consideration, but had not received possession or the OC.

The Commission observed that the developer had accepted more than 10 per cent of the flat’s consideration without first executing a registered agreement, contrary to Section 13 of the Real Estate (Regulation and Development) Act. It also noted that possession had not been delivered after the last extension granted by the Maharashtra Real Estate Regulatory Authority expired on June 30, 2024.

The report said the developer neither appeared before the Commission nor filed a written statement despite receiving notice. The buyers’ evidence therefore remained unrebutted.

The Commission held that the developer could not revive interest demands that had earlier been withdrawn, particularly when the registered agreement did not impose such liability. It directed the developer to provide vacant and peaceful possession within two months, subject to the buyers paying any legitimate balance consideration under the registered agreement.