MahaRERA has directed Veddant Buildcon to hand over a flat in its Ganesh Bella Rossa Phase 2 project in Punawale within 60 days, along with the Occupancy Certificate and other necessary possession documents, according to a report by Pune Mirror.
The order concerns Flat No. 1707 on the 17th floor of Building B, registered under MahaRERA number P52100026780. The complaint was filed by homebuyer Prashant Rahate, who said he had paid the full consideration but had not received physical possession of the apartment.
MahaRERA Member II Ravindra Deshpande also directed the developer to pay delay interest at the State Bank of India’s highest Marginal Cost of Lending Rate plus 2% a year, as well as ₹20,000 towards litigation costs. The interest is to apply to the consideration amounts received by the developer from their respective dates of receipt.
The authority treated October 30, 2025, as the extended possession deadline. The agreement for sale was executed on February 22, 2022, and provided for possession by April 30, 2025, followed by a six-month grace period. MahaRERA fixed the compensable delay period from October 31, 2025, to April 24, 2026. GST, stamp duty, registration charges and other statutory payments were excluded from the interest calculation.
The project’s agreed consideration was ₹49.89 lakh. Rahate told the authority that he paid the remaining ₹7.48 lakh and ₹37,422 in GST on May 2, 2026, after receiving the developer’s final demand. He alleged that the keys were still not handed over and that he had not received a definite date for physical possession.
Veddant Buildcon argued that construction had been affected by a Stop-Work Order issued by the Labour Authority on February 13, 2024. It said work was permitted to resume on May 31, 2024, but that labour shortages, difficulty in remobilising contractors, supply-chain problems and deterioration of construction materials caused further delays.
MahaRERA, however, held that the issuance of a statutory Stop-Work Order did not automatically release the developer from its contractual and legal obligations. The authority did not accept the developer’s explanation as sufficient to exclude the entire delay period.
Rahate had argued that the work stoppage followed a fatal accident at the project site allegedly caused by the developer’s negligence and therefore could not be treated as a force majeure event. The report says MahaRERA considered the competing submissions but did not accept the developer’s explanation as a complete defence to the delay. The accident-related allegation was not independently established in the material reported.
The developer’s advocate, Umesh Raghuwanshi, said the dispute arose from delayed payment and that the buyer’s other claims had been rejected by the tribunal. The developer also contended that possession proceedings had begun after final payment, that some formalities and reconciliation of dues remained, and that it had obtained the completion certificate.
MahaRERA observed that proof of construction completion, a final demand and receipt of the full consideration do not by themselves establish that actual and peaceful possession has been delivered. It said the developer must provide possession together with the required certificate, keys and documents.
The authority rejected Rahate’s separate compensation claim under Section 12 of the Real Estate (Regulation and Development) Act, saying there was insufficient documentary evidence to establish an alleged promise of possession by Diwali 2024. It also declined additional compensation for mental agony and harassment because the supporting independent material was insufficient.
The order allows the parties to adjust their lawful claims and liabilities when possession is handed over. The reported case highlights the distinction between completing construction or issuing a final demand and completing the legally consequential step of giving a buyer peaceful possession with the required approvals and documents.