Power lines along a section of Pune’s Katraj-Kondhwa Road will be shifted underground within nine months after the Pune Municipal Corporation’s Standing Committee approved the work, a move intended to support road widening and reduce risks associated with overhead electrical infrastructure.
The project covers the stretch between Abhay Aranya Society and Lane One in Shivshambho Nagar. Maharashtra State Electricity Distribution Company Limited’s high-tension and low-tension lines currently run above ground on electricity poles along this part of the road.
The accepted tender for the work is worth ₹2,59,75,843, including Goods and Services Tax. The municipal corporation’s Electrical Department had sought an estimate from MSEDCL before preparing a preliminary cost estimate of ₹2,95,21,000, including GST. Eight bids were received during the tender process, of which seven bidders were found eligible.
The Standing Committee recommended accepting the bid submitted by Shewale Electricals. The project will include a 22-kilovolt high-tension underground cable, low-tension cables, ring main unit equipment, feeder pillars, protective pipes and earthing arrangements. Existing electricity poles in the designated stretch will also be removed after the underground system is installed.
The work is linked to the wider effort to widen the Katraj-Kondhwa Road, where overhead poles and electrical lines occupy space along a corridor that carries local traffic and serves residential areas. Moving the lines below ground is expected to clear the existing pole infrastructure from the road environment and address the safety concerns cited by the administration. The supplied report does not specify whether the road-widening work will be completed on the same nine-month schedule.
The same Standing Committee meeting also approved separate electrical and technology-related works in municipal schools. Additional closed-circuit television cameras, along with electrical and network infrastructure, will be installed at an estimated cost of ₹1,99,55,637. The tender submitted by iSecure IT Private Limited was approved, with the work scheduled for completion within eight months.
The committee further approved a ₹99,72,448 tender to supply liquefied petroleum gas cylinders for gas cremators at seven crematoriums in Pune Municipal Corporation’s Circles Four and Five for the next year. Payments will be made at the applicable rate in the month of supply because LPG prices may change under decisions taken by the Central Government.
At Vaikunth Crematorium, the administration has prepared a detailed project report for improvement works after pressure on the facility’s funeral arrangements increased. According to Standing Committee chairperson Shrinath Bhimale, the proposed works include repairing sheds, carrying out concreting where required, improving toilets and upgrading water-supply facilities. The tender for these works is expected to be issued shortly.