Kasauli hillside damage prompts freeze on new land approvals

The Himachal Pradesh High Court has barred the state government from granting new land-purchase permissions to non-agriculturists under Section 118 of the Himachal Pradesh Tenancy and Land Reforms Act, 1972, in Solan district without prior judicial approval. The order came during a public interest litigation concerning alleged illegal hill cutting, tree damage and commercial construction in Kasauli.

A division bench comprising Chief Justice Gurmeet Singh Sandhawalia and Justice Bipin Chander Negi cited what it described as rampant commercial construction and severe ecological damage in the hill town. The court said permissions for non-agriculturists and outsiders had contributed to commercial projects, including apartment complexes, while the state had failed to maintain consolidated data on the approvals issued under Section 118.

The provision was intended to regulate land transfers to non-agriculturists and outsiders in Himachal Pradesh. During the hearing, the bench said safeguards under the law had allegedly been diluted over several decades as permissions continued to be granted. It also raised concerns that private limited companies and separate partnerships may have been used to circumvent the restrictions.

The court examined an inspection report submitted by Kasauli Sub-Divisional Officer (Civil) Mahender Pratap Singh. The report recorded excavation and construction activity at Woodvilla, adjoining the complainant’s property at Ferozi Villa on Lower Mall in Kasauli. It also noted that the roots of existing trees had been exposed.

Following a joint inspection on October 16, authorities directed the developers to stop work and protect the trees. The court identified three developers operating in the area: Reviera Luxury Project Five LLP, Sretan Luxury Project Four LLP and Jambavati Project Reality. It impleaded the three entities, along with senior urban development and town-planning officials, as respondents in the proceedings.

The bench observed that the hillside damage below the Radio Tower was visible from a considerable distance. It said the site had been developed to such an extent that the alteration could be seen from Shimla, approximately 25 kilometres away by air distance. The court further questioned whether the use of different partnerships for the same project had allowed the developers to obtain permissions in a manner that rendered Section 118 ineffective.

Photographic material placed before the court also indicated alleged breaches of the 2025 hill-cutting guidelines. According to the report cited in the proceedings, the guidelines cap single-level excavation at 3.5 metres, limit slopes to 45 degrees and require drainage and slope-stabilisation measures.

The court directed local police to strictly enforce the stop-work notices issued on October 16. It also ordered the Kasauli sub-divisional magistrate to inspect all major commercial projects in the area. The state government has been directed to submit an action-taken report before the next hearing, scheduled for December 7.

The order places new Section 118 permissions in Solan district under direct judicial scrutiny while the court examines whether land approvals, construction activity and hill-cutting controls have been properly coordinated. It also brings the monitoring of major commercial developments in Kasauli within a wider review of environmental and planning compliance.