The Jaipur Development Authority has begun the second phase of an anti-encroachment drive on New Sanganer Road, targeting more than 80 houses and shops in an 800-metre stretch near Gurjar Ki Thadi and Sodala. The action is aimed at restoring the road’s planned 100-foot width, much of which has been reduced to between 40 and 60 feet by unauthorised construction, according to a report by Dainik Bhaskar.
The current operation is taking place from Metro pillar number 84 near Gurjar Ki Thadi to Lajiz Hotel in Sodala. JDA teams have started by removing steps and other structures built outside shops on the footpath. The action affects a commercially active section of New Sanganer Road, where constructions extending into public space have narrowed the carriageway and reduced the space available for traffic and pedestrians.
The operation follows an earlier phase conducted on October 5 between Gurjar Ki Thadi and Vivek Vihar. During that phase, the JDA demolished 50 shops over a stretch of approximately 600 metres. The latest action therefore continues an enforcement process that is being implemented in separate sections rather than across the entire corridor at once.
The broader plan covers approximately three kilometres between the Gurjar Ki Thadi intersection and the Sodala crossing. The JDA has identified 260 unauthorised constructions for removal along this stretch. The authority’s stated objective, as reported, is to clear the encroachments and bring the road closer to its designated width.
The road-width issue is central to the dispute. Although New Sanganer Road is planned as a 100-foot road, encroachments have left parts of it with only 40 to 60 feet of usable width. The difference affects not only vehicle movement but also footpath continuity and the relationship between roadside businesses and public right-of-way. Removing shopfront steps and other extensions is the first visible part of the current phase.
The action is also being linked to the Rajasthan High Court’s strict stance on the matter. The report does not provide details of the court’s order or specify the compliance timeline set for the JDA. It does, however, identify the court’s intervention as a factor behind the authority’s renewed enforcement drive.
The latest operation places the focus on how Jaipur manages roads whose planned dimensions have been reduced over time by private construction. For residents and businesses along the corridor, the immediate changes will involve the removal of structures outside properties and possible disruption during demolition activity. For the authority, the next operational milestone is the completion of the remaining sections of the approximately three-kilometre stretch and the removal of the identified 260 constructions.