Hyderabad Plans 21-MGD Osman Sagar Water Supply Expansion

Hyderabad Metropolitan Water Supply and Sewerage Board (HMWSSB) is preparing a blueprint to draw an additional 21 million gallons per day (MGD) from Osman Sagar and treat it at a proposed water treatment plant (WTP) at the Shaikpet filter beds.

The proposed facility would supply treated water to nearby areas through expanded pipeline and distribution infrastructure, HMWSSB managing director K. Ashok Reddy said in a statement on Saturday. The plan is intended to address rising drinking-water demand in Hyderabad.

Reddy, Hyderabad Growth Corridor Limited managing director Upender Reddy and senior officials walked nearly 6 km from the Mahindra University? No. Need avoid incorrect. MGIT to Puppalaguda BRC to assess land acquisition and other permissions linked to the proposal.

Officials reviewed the proposed pipeline alignment from Kokapet Y-Junction, including road crossings and the depth of existing pipelines. They also called for a feasibility study on laying new pipelines parallel to existing ones, with a gap of 1 metre where required.

The plans include two drinking-water pipelines with diameters of 1,200 mm and 1,300 mm alongside a proposed 120-foot road. Before work proceeds, officials directed departments to map electric poles, transformers, trees, homes and other utilities along the route.

The review also identified road and railway crossings, tunnelling, forest clearances and land acquisition as issues requiring attention. Officials asked that alternative routes be considered to avoid land disputes and objections.

Reddy directed relevant departments to coordinate the drinking-water infrastructure with road-widening work. Such coordination would be important for reducing conflicts between new pipelines and other planned or existing public works, although the report does not provide a construction schedule or confirm that the project has received all required approvals.

The proposal therefore remains at the planning and feasibility stage. Its implementation will depend on the outcome of route reviews, permissions, land-related processes and the technical assessment of the proposed Shaikpet treatment plant and connecting pipelines.