Eight months after sewer-line work began on Lane 1A in Gurugram’s Sector 17A Defence Colony, the road remains unpaved, with uncovered manholes and no vehicle access, leaving elderly residents struggling to reach their homes and the neighbourhood park.
The work began in March after residents were told at a March 2 meeting that the sewer line would be laid within six weeks and that the road would soon be made motorable. Lane 1A, the longest road in the sector, connects several homes to the main road.
Ward councillor Anoop Singh and Municipal Corporation of Gurugram (MCG) officials said the contractor responsible for resurfacing the road after the sewer work had abandoned the project and was refusing to return. Singh said multiple notices had been issued and that the civic body was now considering blacklisting the contractor.
The disruption has been particularly difficult for older residents. Kamla Yadav, 82, said she had stopped visiting the neighbourhood park because she feared tripping on the damaged road. Sushma Gehlot, 76, said she could not walk safely on the stretch and that app-based drivers refused to come to her house because of the road condition.
Access has also been affected by the closure of Vikram Shastri Marg, another major road into the colony. The road was closed after a drain burst during work to connect it to the new sewer line under Lane 1A. With both routes disrupted, residents said Bata Road had become the colony’s only entry point. Excavated mud and soil had also obstructed the entrance to the neighbourhood park, they said.
Residents submitted a complaint to the MCG in June seeking temporary repairs before the monsoon. A copy of the complaint, reviewed by Hindustan Times, showed that civic officials later inspected the site and directed the contractor to resurface the road, but residents said no work followed. An MCG official, speaking anonymously, confirmed that the complaint had been received and the site inspected, and said the contractor had failed to act.
The official attributed delays in laying the sewer line to multiple water-supply connections and bundles of electricity cables at the site. Residents, however, said the civic body had not provided the residents’ welfare association with a schedule for completing the work. Ameeta Dahia, the association’s general secretary, said residents had to assess the status of the project each day because there was no plan, information or timeline.
MCG chief engineer Vijay Dhaka attributed the recent disruption to restrictions under the Graded Response Action Plan, or GRAP, saying that labourers had left after GRAP was invoked. He described the situation as difficult for residents and said resurfacing would begin soon, with the road expected to be improved beyond its earlier condition.
Sukh Chain, estate manager of Defence Colony, said the prolonged disruption was especially concerning because many residents were older defence personnel living alone while their children worked in other metropolitan cities or abroad. The episode illustrates how delays after utility work can extend beyond construction inconvenience: when reinstatement, access management and public communication are not coordinated, a local sewer project can restrict daily mobility for months.