The Delhi Jal Board has received permission to lay and replace about 1,000 km of water pipelines across the capital, with the agency also allowed to excavate and restore roads under a special arrangement approved by the Municipal Corporation of Delhi’s standing committee.
The approval was granted at a standing committee meeting on Thursday for a World Bank-supported project covering about 96 sq km. The areas listed include Timarpur, Model Town, Sadar Bazar, Chandni Chowk, Matia Mahal, Ballimaran, Karol Bagh, Patel Nagar, Rajinder Nagar, Jangpura and RK Puram.
Under the arrangement, the Delhi Jal Board will be responsible for both the excavation and reconstruction work. Before digging, it must deposit a security amount equivalent to 10% of the estimated restoration cost or Rs 2 lakh, whichever is higher. Reconstruction must begin within 48 hours of the excavation being completed, according to the report.
An independent third-party agency will inspect the quality of the restoration. The security amount will be returned after the work is found satisfactory and the required certificates have been submitted.
The decision follows the MCD’s discontinuation in 2024 of the earlier ‘dig and restore’ system after complaints about poor-quality road repairs. Under the replacement ‘dig and deposit’ system, agencies carrying out excavation deposit the restoration cost, while the concerned agency undertakes the road repair.
The special permission is limited to the World Bank-assisted project, officials clarified at the meeting.
AAP councillor Praveen Kumar opposed the proposal, saying agencies often carry out patchwork instead of fully reconstructing roads, leading to faster deterioration and continued inconvenience for residents. The new conditions are intended to address restoration quality, but their effectiveness will depend on timely inspections and enforcement during the pipeline works.