HomeBreaking NewsBMC Tightens Dust Controls at Mumbai Coastal Road North Sites

BMC Tightens Dust Controls at Mumbai Coastal Road North Sites

The Brihanmumbai Municipal Corporation has directed officials and contractors working on the Mumbai Coastal Road North project to strengthen pollution-control measures, including covering excavated material and deploying adequate water sprinklers at construction sites.

Additional Municipal Commissioner (Projects) Abhijit Bangar issued the directions during an inspection of the project on Wednesday, November 25, according to a BMC statement reported by Mid-Day. He also instructed teams to ensure that excavated material is properly covered during storage and transportation and that construction safety measures are followed.

The Coastal Road North project comprises seven packages, with work underway across all packages. The civic body is targeting completion by December 2028.

During the inspection of Package E, Bangar visited Gorai Jetty and reviewed the temporary access bridge. The alignment between Sector 8 in Charkop and Borivali has been divided into four sections, with separate plans for each phase. Manpower and machinery have been deployed for the ongoing work, the report said.

A cable-stayed bridge is planned at Gorai Jetty under the package. Bangar directed officials to execute the work carefully and avoid delays, given the expected construction time for the bridge.

He later inspected work on a temporary access road at the Borivali Interchange under Package F. The package includes a large temporary access bridge at the interchange. Officials were instructed to carry out piling simultaneously using four piling gantries and to divide the package into four phases for the deployment of manpower and machinery.

Construction at the Dahisar Interchange was also reviewed, with officials directed to accelerate the work. Deputy Commissioner (Infrastructure) Girish Nikam, Chief Engineer (Roads and Traffic) Mantayya Swamy, Deputy Chief Engineer Vaibhav Gandhi, engineers and consultants attended the inspection.

The dust-control directions apply as construction activity continues across the project’s sites, including the handling and movement of excavated material.