Bengaluru’s fourth phase of white-topping will cost Rs 2,321.17 crore for 130.85 km of roads, taking the reported estimate to nearly Rs 17.85 crore per kilometre. The figure is 48% higher than the Rs 12 crore per kilometre benchmark cited for Phase III, but officials said the latest estimate covers more than concrete paving.
The state Cabinet has approved the project, which will cover 88 roads divided into 12 packages. Bengaluru Smart Infrastructure Ltd (B-SMILE) has been entrusted with implementing the works. According to officials cited by Deccan Herald, the project is designed as “full corridor development” based on TenderSURE standards.
The reported scope includes footpath development, rainwater drainage, streetlighting, junction improvements and utility-related work. Officials said B-SMILE would also bear the cost of water supply and sewerage works, as well as shifting utilities belonging to Bescom and KPTCL. Excluding those utility expenses, the cost of white-topping, footpaths and rainwater drainage was put at Rs 14.21 crore per kilometre.
The distinction is important for assessing the increase against earlier phases. The earlier benchmark of Rs 12 crore per kilometre did not represent the same reported scope as the current estimate, according to officials. The project therefore combines road reconstruction with a wider corridor upgrade, making the per-kilometre comparison less like-for-like than the headline increase suggests.
The roads shortlisted for Phase IV include Old Madras Road between Benniganahalli and KR Puram railway station, Dr Rajkumar Road, Hennur-Bagalur Road between the Outer Ring Road and Sparsha Hospital, and Alur Venkata Rao Road between Mysuru Road and KR Road.
B-SMILE officials said the agency surveyed 500 km of roads across five city corporations before selecting the 88 stretches. Of the selected roads, 71 are shorter than 2 km and 59 are at least 18 metres wide. B-SMILE Technical Director BS Prahallad said several shorter stretches were deficient or missing links intended to connect existing white-topped roads into a continuous network, particularly in central business district areas. Some longer stretches are located in the city’s outer areas, including Bannerghatta Road, Andrahalli Main Road and Medahalli Main Road.
Greater Bengaluru Development Minister Krishna Byre Gowda said the programme would provide durable, pothole-free roads along with scientifically designed walkable footpaths, rationalised junctions and streetlighting infrastructure. These elements indicate that the project is intended to address corridor design and pedestrian movement alongside pavement durability.
The programme also inherits concerns from earlier phases. Motorists have objected to the slow pace of construction, with some stretches reportedly taking several years to complete. Phase III covers 134 km under a Rs 1,600-crore project, at a reported cost of Rs 12 crore per kilometre. Phase II covered 63.26 km at Rs 735.52 crore, while Phase I covered 93.47 km at Rs 972.68 crore.
The reported progression in per-kilometre estimates—from Rs 10.40 crore in Phase I to Rs 11.62 crore in Phase II, Rs 12 crore in Phase III and Rs 17.85 crore in Phase IV—shows why scope transparency and delivery timelines will be central to evaluating the latest programme. For residents, the outcome will depend not only on the finished concrete surface but also on whether footpaths, drainage, junctions and utility works are completed as an integrated corridor rather than as separate, delayed interventions.