Bengaluru development minister Krishna Byre Gowda has ordered urgent pothole repairs and a review of delayed road works on the Varthur-Gunjur stretch of State Highway 35 after severe congestion left schoolchildren spending hours in traffic. Contractors were warned that they could face action if the delays continue.
Gowda convened a high-level meeting attended by officials from the Karnataka Road Development Corporation Ltd (KRDCL), Bescom, Bengaluru East City Corporation, the Greater Bengaluru Authority and the state government. Senior officials, including the additional chief secretary, also participated in the review, according to a report by The Times of India.
The minister directed contractors to repair potholes and damaged sections between Brigade developments and Gunjur immediately. Repairs on Varthur-Kodi Road were also prioritised. The instructions cover stretches where incomplete road works and deteriorating surfaces have contributed to delays and worsening traffic conditions.
The meeting also focused on delays in shifting electric poles and other power infrastructure. Bescom officials, including the utility’s managing director, were questioned about the pending relocations, which residents and officials have repeatedly identified as a factor slowing work along the corridor. Land acquisition difficulties were also cited during discussions on the delay.
The review followed widespread public outrage over congestion on SH-35. Some schoolchildren were reportedly taking more than two hours to travel a few kilometres in school buses. The disruption has highlighted how unfinished road construction, utility relocation and daily commuter movement are interacting on one of Bengaluru’s rapidly urbanising eastern corridors.
The additional chief secretary has called both contractors to a meeting on Monday to explain the delays. A source familiar with the discussions told The Times of India that the ACS could recommend replacing the contractors if they fail to provide a concrete explanation. The report did not identify the contractors by name.
There were signs of activity at the site after the review. Contractor representatives visited parts of the Varthur-Gunjur stretch to assess pending work, while the KRDCL chief engineer inspected the corridor. Local representatives and residents have called for visible progress, including immediate pothole repairs and faster resolution of the pole-shifting work. The next formal step is the contractors’ meeting with the additional chief secretary.