HomeAnalysisPhased wind-farm repowering could ease India’s ageing turbine upgrade challenge

Phased wind-farm repowering could ease India’s ageing turbine upgrade challenge

India’s ageing wind farms may now be able to replace turbines in stages rather than shut down or overhaul an entire project at once, according to a new Standard Operating Procedure reported by Livemint from the Central Electricity Authority (CEA). The procedure covers repowering wind-power projects that operate a mix of old and new wind turbine generators during the transition.

The framework, titled “SOP for Repowering of Wind Power Projects with Mixed WTGs under the CEA Connectivity Regulations”, sets a minimum batch size of 33% of a project’s installed capacity for key compliance and validation steps. This gives developers a defined route to begin replacing older turbines while retaining some existing units at the site.

The change addresses a practical difficulty in upgrading older wind projects. Replacing all turbines simultaneously can require significant capital, coordination and downtime. Under the reported procedure, repowering can be spread across multiple stages, allowing developers to manage the transition without requiring a plant-wide switch at the outset.

The phased approach does not provide unrestricted permission to operate the full project while compliance work remains incomplete. Until the required compliance is achieved, the project may schedule power injection at its Point of Interconnection only up to its compliant capacity. This limits the amount of electricity that can be injected into the grid during the transition.

The procedure also provides transitional treatment for turbines commissioned before the 2019 amendment to the CEA’s Technical Standards for Connectivity to the Grid Regulations. These legacy turbines will generally not need to be retrofitted to current technical standards if they are scheduled for replacement, except where the SOP specifically requires it.

That treatment is not a blanket exemption. The older turbines must continue to comply with the regulatory standards applicable when they were commissioned. For steady-state simulation studies, active and reactive power injections from older wind turbine generators that do not comply with current CEA rules will be set to zero under the interim arrangement.

The arrangement will continue until the earliest of three triggers: completion of the repowering process, the end of the project’s life, or expiry of the applicable power purchase agreement or Energy Wheeling Agreement timeline. After that point, every turbine at the site must either comply with prevailing CEA connectivity regulations, be repowered or be decommissioned.

Grid visibility remains a central condition of the phased process. Mixing older and newer turbine models can change how a wind plant behaves electrically, making monitoring and accurate simulation important for grid operators. According to Livemint, developers must regularly share data from power quality meters, disturbance recorders or digital fault recorders with the transmission utility and grid operator during the transition.

Harmonic filter compliance and validation of the complete renewable-energy plant simulation model can be completed in batches after each repowering phase reaches at least 33% of installed capacity. Partial or phased model validation will also take place at each turbine-replacement milestone. A full and final validation is required after the entire repowering exercise is completed.

For developers, the procedure could reduce the immediate financial and operational burden of upgrading older sites. For transmission utilities and grid operators, it establishes limits on interim power injection and requires continuing technical data, rather than treating a partially repowered project as fully compliant.

The reported framework therefore links investment flexibility with staged grid oversight. Its effectiveness will depend on how developers schedule replacement batches, how quickly technical validation is completed and whether the required monitoring data is consistently supplied. The available report does not provide project-level examples or quantify the number of wind farms that may be covered by the procedure.