The Aroor–Thuravoor elevated highway in Kerala has entered structural load testing, with the National Highways Authority of India completing the first test using nine trucks carrying a combined 325 tonnes, Malayala Manorama reported on November 28.
The testing is intended to assess the elevated highway’s structural strength and load-bearing capacity before the project is completed. Eight more tests covering different types of spans are planned, with each test expected to take four to five days. The authority is targeting completion of the testing process by next month, according to the report.
The tests are being conducted in accordance with Indian Roads Congress guidelines. The reported procedure includes a detailed inspection for cracks, followed by sensor-based measurement of stress and movement. Trucks carrying about 30 tonnes each are to be stationed on the structure in stages, allowing engineers to observe bending under progressively increased loads.
The testing also includes running trucks across the elevated highway at speeds of 10 to 40 kilometres per hour to assess structural changes. The structure is then monitored in detail for 24 hours, the report said.
The Aroor–Thuravoor project is being built as an elevated section of the national highway in Alappuzha district. The elevated highway was initially planned for 12.75 kilometres, but the reported length has increased to 13.23 kilometres, including a 200-metre elevated section and a 280-metre approach road. It is supported by 364 piers, each about nine metres high.
The project cost is reported at Rs 2,200 crore. Remaining works include approach roads, expansion joints, noise barriers and street lighting. The authority is targeting completion and handover of the project by March 2027, subject to the completion of construction and testing.
The load tests are a key quality-assurance stage before the elevated corridor is opened to traffic. Their findings, along with the remaining construction work, will determine whether the project is ready for public use within the stated schedule.