Mumbai’s first large-scale waste-to-energy facility at the Deonar dumping ground is 93% complete, with the Brihanmumbai Municipal Corporation planning to begin trial operations in December, according to a report by The Times of India cited by the Free Press Journal.
The Rs 648-crore plant is expected to become operational in early 2027. It has been designed to process 600 tonnes of fresh municipal waste a day and generate up to eight megawatts of electricity.
The proposed trial period is expected to last one to two months. During this phase, the civic body will assess the facility’s actual power output and operating performance before moving towards commercial electricity generation.
Once the trials are completed, the BMC is expected to approach the Maharashtra Electricity Regulatory Commission for approval to sell the power produced. The electricity is likely to be supplied to Adani Electricity, with the resulting revenue adjusted against the civic body’s electricity bills. The tariff has not been finalised and could range between Rs 5 and Rs 10 per unit, the report said.
The project was initially scheduled for commissioning by October 2025. According to the report, its completion was delayed by logistical difficulties, an increase in the proposed power-generation capacity and pending statutory clearances.
The plant’s planned capacity also highlights a key limitation: it will process only fresh municipal waste and will not treat the legacy garbage accumulated at Deonar over several decades. Nearly one million tonnes of old waste had to be scientifically relocated and stabilised within the dumping ground before construction could begin.
The BMC has separately appointed Navayuga Engineering Ltd to undertake bioremediation of 18.5 million tonnes of legacy waste, manage the disposal of processed and segregated material, and reclaim 110 hectares of land at the site. This work is distinct from the new waste-to-energy facility and remains central to the long-term redevelopment of the Deonar dumping ground.
The distinction matters for Mumbai’s waste strategy. Even if the new plant reaches its planned capacity, it will address only a portion of the city’s daily fresh-waste stream and will not by itself resolve the environmental and land-use burden created by accumulated waste at Deonar.
The report also notes that Mumbai currently operates two BMC-run construction and demolition waste recycling facilities, at Dahisar and Shilphata. Together, they have a stated processing capacity of 1,200 tonnes a day. Since their launch in 2024, the facilities have collectively handled about 3.3 lakh tonnes of debris, including nearly 2.11 lakh tonnes that has been processed.
The next operational milestones for the Deonar plant are the start of trials, measurement of power generation, completion of statutory processes and a decision on the electricity tariff. The facility’s performance will determine how much of the planned waste-processing and power-generation capacity can be achieved in practice.