Deoli underpass height blocks buses, triggers repair demand

A height-restricted underpass on the Butibori–Tuljapur National Highway bypass is disrupting bus and heavy-vehicle movement on the Deoli–Yavatmal route in Wardha district, according to a report by Loksatta.

The underpass is reportedly about 3.5 metres high on one side, preventing taller Maharashtra State Road Transport Corporation buses, private travel buses and heavy vehicles from using the route. The disruption is also affecting traffic linked to State Highway 322 and Deoli’s industrial area, the report said.

Deoli municipal chief Kiran Thakare has written to the project director of the National Highways Authority of India (NHAI), demanding that the reported technical defect be corrected and that the underpass provide a height of 5.5 metres. Thakare warned that an agitation would be launched if urgent repairs were not undertaken.

Deoli is a major taluka centre through which State Highway 322 passes. The town also has a large industrial area, resulting in regular movement of state transport buses, private buses and heavy vehicles along the corridor.

The report attributed the height problem to an alleged construction error at a curve in the bypass. According to the complaint cited by Loksatta, a mistake in the curve’s super-elevation caused the slab to be higher at one end and slope down towards the other, reducing clearance at the underpass.

Loksatta reported that the municipal chief’s letter referred to Indian Roads Congress and NHAI requirements under which an underpass on a state highway carrying heavy traffic should have a minimum clearance of 5.5 metres. The report did not include a response from NHAI or the contractor.

The reported obstruction has stopped several bus services from entering areas that they previously served and has created an access problem for industrial and freight traffic. The next steps will depend on an inspection by the highway authorities and a decision on how the underpass can be modified to restore the required clearance.