HomeBreaking NewsMira-Bhayandar plans first Surya water supply phase in January

Mira-Bhayandar plans first Surya water supply phase in January

Mira-Bhayandar is expected to receive 50 to 60 million litres per day (MLD) from the first phase of the Surya Regional Water Supply Project in January, according to a report by Loksatta. The planned supply is intended to ease recurring shortages in the city, where rising population and demand have made existing allocations inadequate.

The first water is planned for the first week of January. To prepare the network, flushing of internal water pipelines is scheduled to begin next week. The process is expected to take about a month, the report said.

Mira-Bhayandar currently receives around 211 MLD of water daily from STEM and the Maharashtra Industrial Development Corporation. The city has been allocated an additional 218 MLD through the Surya project, but that supply has not yet reached residents because of obstacles involving electricity supply and the construction of electrical towers.

A high-level review meeting on the project was held at the Mumbai Metropolitan Region Development Authority office in Mumbai. The meeting included planning to start the first-phase supply from the beginning of January and directed the municipal administration to undertake the internal pipeline flushing work.

The report also said that work on a 132-kilovolt power-supply project was planned for completion by December 31. The power infrastructure is a key requirement for bringing the Surya project’s water into the city.

If the first phase begins as planned, it would provide additional daily supply to a city that has faced repeated water shortages. However, the reported January start remains a planned schedule. The full benefit of the sanctioned 218 MLD allocation will depend on completion of the associated power, electrical-tower and distribution-network works.