Construction-quality checks were carried out at the earth-cum-rock-fill dam of the Polavaram irrigation project after Polavaram Project Authority chief executive officer Sanjeev Vohra inspected the site on Thursday.
The inspection focused on the compaction and stability of the filled material. Selected portions of the embankment were excavated to a depth of about one metre with an excavator to assess the compactness of the underlying layers.
The excavated soil was subsequently refilled and compacted using a sheep-foot roller. A comparison of compaction levels before and after the exercise showed no significant variation, according to the report.
Vohra examined the methods used to place soil and rock and directed officials and the construction agency to follow prescribed quality standards at every stage of the work. The checks are part of on-site construction-quality oversight for the dam’s filled embankment.
Separately, a three-member expert team from the Central Soil and Materials Research Station conducted a three-day assessment of construction materials at the project site. The report did not provide the team’s findings or indicate whether any corrective measures were recommended.
The inspection places compaction testing and material assessment at the centre of the project’s current quality-control activity. Further technical findings would be needed to establish whether the assessments lead to changes in construction methods or additional work at the dam.