HomeAnalysisShaktipeeth Expressway faces land-acquisition test in Maharashtra

Shaktipeeth Expressway faces land-acquisition test in Maharashtra

The proposed Shaktipeeth Expressway is facing intensified opposition in Maharashtra’s Sangli and Kolhapur districts, where farmers have challenged land surveys linked to the project. The protests have brought the proposed highway’s land requirements, revised cost and alignment changes back into focus.

Farmers in Mahuli, Nagewadi and Bhagyanagar villages in Sangli’s Khanapur taluka confronted officials conducting surveys, according to the report. Swabhimani Shetkari Sanghatana president Raju Shetti led an eight-hour sit-in at Mahuli. Police detained several protesters as tensions rose, while some demonstrators damaged surveying equipment, the report said.

A separate confrontation took place in Konavade village in Kolhapur’s Bhudargad taluka, where farmers objected to an early-morning survey conducted under police protection. The survey was scheduled to cover Konavade, Mhaswe, Nilpan and Nadhavade, among other villages. Protesters reportedly seized a survey tripod and set it on fire.

The farmers’ objection is centred on the proposed acquisition of agricultural land. They have argued that the expressway could affect fertile farmland and disrupt livelihoods built around cultivation. They have also questioned why surveys are continuing despite opposition from villages along the proposed alignment.

The project has also become a political issue. NCP (SP) MP Supriya Sule said the government should take farmers’ concerns seriously. Citing the state’s financial position, she said her party was not opposed to infrastructure development but that the financial implications of large projects should be considered. She also said addressing farmers’ concerns should be the government’s immediate priority.

The Shaktipeeth Expressway is planned as a six-lane greenfield highway connecting Pavnar in Wardha district with Patradevi in Sindhudurg, near the Maharashtra-Goa border. The proposed route is intended to connect eastern Maharashtra with the Konkan region and pass through 12 districts, including areas associated with important religious destinations.

The alignment was revised in July, extending the proposed length by 54 km to 856.7 km, according to figures cited from The Indian Express. The estimated project cost rose from about ₹80,000 crore to approximately ₹1 lakh crore. The revised route includes a 40-km stretch through Satara district, covering Gondawale and Shikhar Shinganapur, along with changes in Nanded, Hingoli, Parbhani, Solapur, Sangli and Kolhapur.

The project is expected to require approximately 8,760 hectares of land. That requirement makes the survey process a significant stage for affected communities, even though the full implications for individual landholders depend on the final alignment and acquisition process. The available report does not provide details of compensation packages, rehabilitation measures or a revised schedule for land acquisition.

Supporters of the expressway expect it to improve road connectivity between eastern Maharashtra and the Konkan region. Once completed, it is expected to reduce travel time between Nagpur and Goa from around 18 hours to eight hours. Those projected benefits are being weighed against concerns over the loss of agricultural land, disruption to village economies and the financial burden of the expanded project.

The immediate challenge for the project is therefore not only construction. It is the ability to conduct surveys and pursue alignment decisions while addressing objections from communities whose land may be affected. The recent confrontations in Sangli and Kolhapur show that the land-acquisition process has become a central test of public acceptance for the proposed corridor.