HomeBreaking NewsBengaluru Sets February Target for Road and Drain Works

Bengaluru Sets February Target for Road and Drain Works

Bengaluru’s road and stormwater-drain works across the five municipal corporations under the Greater Bengaluru Authority are to be completed on priority, with Urban Development Minister Krishna Byre Gowda setting February as the target for finishing the ongoing works.

The minister issued the directions at a progress review meeting with officials from the five corporations, according to a report by Vijay Karnataka. He also instructed officials to accelerate road development and rajakaluve, or stormwater-drain, projects and ensure that allocated funds are used effectively.

Byre Gowda said residents had submitted numerous complaints about roads. He attributed delays partly to the monsoon and to a rise in asphalt prices linked to adverse conditions in Middle Eastern countries. He said payments for asphalt work were being made on a star-rate basis and directed officials to complete projects within the stipulated period.

White-topping has been prioritised under the road programme. The government plans to develop 88 white-topped roads covering 130 kilometres at a cost of Rs 2,321 crore, the report said. Work on 120 km is already under way, although permission has not been secured for around 20-25 km because of traffic constraints. Officials have been told to complete work at locations where construction can proceed by December, while coordinating with Bengaluru Water Supply and Sewerage Board projects in areas where both works are under way.

The minister said Rs 487 crore had been set aside separately for Outer Ring Road development. Of the 2,875 km of road works planned overall, 553 km had already been asphalted. Tenders for another 100-200 km were reportedly at the final stage, and officials were directed to begin work immediately in locations where construction had not started. Contractors were asked to deploy additional staff to accelerate delivery.

Under the Ward One campaign, pothole repairs and broader ward-level works, including cleaning and essential infrastructure improvements, are being taken up. The campaign is targeted for completion by the end of December.

The government is also developing around 200 km of stormwater drains following a survey, with attention to previously undeveloped peripheral areas. The report said the civic authorities had taken possession of up to about 20 acres of encroached land for drain development. Buffer roads alongside the drains are also under construction, supported by an allocation of Rs 200 crore.

Officials have been given a three-month target to complete concrete road works other than asphalt and white-topping projects. Byre Gowda said road development should include footpaths, drain desilting and other related infrastructure rather than being limited to resurfacing.

The review also outlined plans for a unified dashboard carrying live information on road works across the five corporations. Geographic information system data from different departments is to be integrated, while the Integrated Financial Management System is to be upgraded for progress-linked automated billing. Dash-cam data is proposed for monitoring road conditions, with project information to be made available online to improve transparency.

The reported project portfolio includes Rs 1,000 crore for 629 km under the CMIDP, Rs 1,241 crore for 787 km under the SIP, Rs 2,000 crore for 1,040 km under a special grant, Rs 506 crore for 250 km in five peripheral Assembly constituencies under the VDP, and Rs 647 crore for 175 km through municipal corporation funding.