Bengaluru’s 19.75-km Outer Ring Road Metro corridor is targeted to open by mid-2027, Greater Bengaluru Development Minister Krishna Byre Gowda said on Tuesday, as trial runs are set to move beyond Doddanekundi within a month.
The KR Pura–Silk Board line, part of Phase 2A of Bengaluru’s Blue Line, currently has trial operations over 6.5 km and four stations: KR Pura, Saraswathi Nagar, DRDO Sports Complex and Doddanekundi. The trial train was operated from KR Pura to Doddanekundi during the minister’s inspection.
Gowda said automatic signalling work is expected to be completed by February, with the safety certification process scheduled to begin in March. The corridor is targeted for commissioning in seven to eight months, he said.
The ORR corridor will serve one of Bengaluru’s most congested and economically important employment districts. Phase 2A was approved by the Centre in July 2021, and construction began in September that year. The line has 13 stations.
Bengaluru Metro Rail Corporation Ltd (BMRCL) said piling, pile caps, piers, and U-girder casting and erection had reached 100% completion. Station entry and exit structures were 85% complete, while roofing was 68% complete. Work on roofing, painting, granite fixing and handrails was continuing.
Track laying has been completed on 37.1 km of the 39.2-km corridor. Third-rail installation, station electrical works and cable laying are under way, while auxiliary and traction substations are being commissioned at the stations.
The third rail between the depot and Doddanekundi has been energised with a 750-volt direct-current traction supply through the depot and the Saraswathi Nagar traction substation. BMRCL said installation beyond Doddanekundi would allow trains to receive traction power towards Silk Board.
The current tests will examine the compatibility of fixed structures, tracks and traction installations with the train’s kinematic gauge at low speeds. Dynamic testing of trains, including signalling, traction, braking and train-signalling integration, will follow.
The minister also directed officials to expedite work on the KR Pura–Hebbal section of Phase 2B, a 38.44-km corridor that will connect KR Pura with Kempegowda International Airport through Hebbal. The entire 58.19-km Blue Line is targeted for completion within 18 months, according to Gowda.
The proposed Red Line, or Phase 3A, is still awaiting approval from the Centre, the minister said. Karnataka officials held a meeting in Delhi on the project, but no final decision had been taken. The state has sought approval for a double-decker viaduct incorporating road flyovers along two elevated stretches: the 14-km Sarjapur–Iblur section and the 2.45-km Agara–Koramangala 3rd Block section.
The expansion is also raising questions about BMRCL’s future operating costs. Gowda said Karnataka was exploring ways to help the metro corporation meet operating expenses without government grants. Although BMRCL currently has an operating surplus, annual depreciation could rise to Rs 600–700 crore as the network ages and equipment requires replacement.
BMRCL’s depreciation stood at Rs 576.79 crore in 2025–26, according to its latest annual report. The minister said operating expenditure would increase as more lines open, while Karnataka continues to bear loan repayments, operational cash losses, construction cost escalations and exchange-rate variations.
According to the report, BMRCL’s finance cost rose from Rs 560.91 crore in 2024–25 to Rs 1,793.03 crore in 2025–26. Exchange-rate variation increased from Rs 263.75 crore to Rs 1,444 crore during the period. Gowda said the rupee’s decline from around Rs 70–80 to about Rs 100 to the dollar had increased the loan burden by nearly 30%.
Karnataka has asked the Centre to share Bengaluru Metro’s exchange-rate variation and operational cash losses, as it does for Delhi Metro. As additional corridors open, foreign loan costs are transferred from interest during construction to the profit-and-loss account, increasing the financial burden recorded by the system.