Land acquisition procedures have begun for runway safety and expansion work at Thiruvananthapuram International Airport, reviving a project that missed its earlier completion target because of land, coordination and statutory approval hurdles.
District Collector K.S. Anju confirmed that the process started after the Airports Authority of India (AAI) submitted a formal request to the district administration. The proposed work is intended to bring the airport’s runway end safety areas (RESA) into compliance with applicable standards.
The project requires around 22 acres across Pettah, Muttathara and Kadakampally. A Kerala government proposal approved in March 2026 covered 19.76 acres, comprising 4.19 acres of private land and 15.57 acres of government land. The source report said a November 2026 notification covers private land in Pettah and Muttathara.
The final list of affected properties, however, and the dates for possession have not yet been confirmed through official notifications, according to the report. The administration is also examining whether a Social Impact Assessment is required under land-acquisition legislation.
The acquisition is one part of a wider set of implementation issues. The project requires coordination over land associated with BrahMos Aerospace, the relocation of the Chackai fire and rescue station, and changes to a section of the Chackai-Shanghumugham road. These steps will need to be resolved before construction can proceed fully.
The runway safety work had originally been targeted for completion by September 2024. Delays in acquiring and transferring land, coordination involving defence authorities, the fire-station relocation and pending statutory procedures led the Directorate General of Civil Aviation to extend the programme. The revised completion window is 2027–2028.
The district administration aims to complete the land handover during the next financial year, subject to the required clearances. The source report said AAI or the private airport operator would bear the full cost of acquiring the land and shifting affected facilities.
For residents and property owners in Pettah, Muttathara and Kadakampally, the immediate significance lies in the next administrative steps rather than construction activity. Formal notifications will establish the affected properties and acquisition terms, while decisions on the road realignment and fire-station relocation will determine how access and emergency-response arrangements are managed around Chackai.
The project’s progress therefore depends on more than the restart of acquisition proceedings. Land transfer, impact-assessment requirements, inter-agency coordination and statutory approvals remain linked actions. Until these are completed, the revised 2027–2028 timeline remains dependent on the administration’s ability to resolve the outstanding issues.