HomeAnalysisSupertech Stalled Projects Face More Delay After CJI Recusal

Supertech Stalled Projects Face More Delay After CJI Recusal

Supertech’s stalled projects face another procedural delay after Chief Justice of India Surya Kant recused himself from hearing a petition concerning the real estate company’s insolvency process and the interests of its homebuyers, according to Live Hindustan. The Chief Justice said one of the applicants was personally known to him and that a special bench would therefore be constituted to hear the matter.

The development came after a bench comprising the CJI and Justices Joymallya Bagchi and V. Mohana had reserved its order on 16 November, the report said. A new bench will now be formed for the case.

The dispute involves 16 incomplete Supertech projects for which the National Buildings Construction Corporation (NBCC), a government company, was assigned responsibility for completion following an order of the National Company Law Appellate Tribunal (NCLAT). Live Hindustan reported that more than 20,000 flat buyers are affected by the stalled developments.

According to the report, 23 months have passed since the NCLAT order, but construction has not started on any of the projects. The arrangement had raised hopes among buyers that unfinished homes would be completed and that families would eventually be relieved of the combined burden of rent and home-loan repayments.

The 16 projects named in the report are Cape Town, Romano, North Eye, Sports Village, Mikasa, Meerut Sports City, Green Village Meerut, Up Country, Czar, Eco Village 2, Eco Village 3, Eco Village 1, Eco City, Hill Town, Aravalli and River Crest.

The immediate institutional issue is whether NBCC will continue with the completion process and under what terms. In an earlier hearing, NBCC reportedly told the Supreme Court that it would prefer to withdraw from the assignment if homebuyers did not want the company to remain involved. The report also said that NBCC had sought various concessions, which buyer representatives have opposed.

The delay has translated into a prolonged housing and financial crisis for families who booked homes years ago. Buyer Archana Sharma told Live Hindustan that she booked a flat in 2015, had repaid her entire home-loan instalment and was still paying rent because the home had not been delivered. Another buyer, Manoj Garg, said he booked a flat in 2011 but had received neither the apartment nor a refund.

Abhishek Kumar, president of the homebuyers’ group NEFOWA, said the wait for thousands of families was continuing and that there was still no clarity on when construction would begin or when individual projects would be completed. Buyer representative Sushil Bhati said the group would continue opposing concessions sought by NBCC that it considered contrary to buyers’ interests.

The recusal does not decide the underlying insolvency or construction dispute, but it means the matter will be heard by a newly constituted bench. For buyers, the reported consequence is another interruption in a process that had already failed to produce construction progress nearly two years after the tribunal’s intervention. The unresolved questions include the completion framework for each project, the terms of NBCC’s participation, the treatment of buyer interests and the timetable for restarting construction.