The Supreme Court has restrained coercive recovery action against homebuyers in a stalled Sonipat housing project until a commercial court determines whether the buyers were actually in default and whether the lender disbursed funds in accordance with the tripartite agreement.
The order arose from a petition by buyers in the Krishna housing project developed by Raheja Developers, which has entered insolvency proceedings before the National Company Law Tribunal. The buyers told the court that they had not received possession of their flats, while the State Bank of India had initiated recovery proceedings against them in a commercial court in Saket, New Delhi.
A bench comprising Chief Justice of India Surya Kant and Justices Joymalya Bagchi and V Mohana said that no interim direction requiring payment of instalments could be issued unless there was a categorical finding that the homebuyers were in default. It also directed the civil court not to take coercive action against the petitioners or similarly placed homebuyers before examining that issue.
The court placed particular emphasis on the relationship between the lender and the developer. It said the commercial court must determine whether there was a nexus between the builder and bank officials and whether the bank had released loan amounts strictly in accordance with the tripartite agreement.
These agreements typically involve the buyer, developer and lender. In construction-linked arrangements, the loan is expected to be released in stages corresponding to progress at the project. According to the report, the buyers alleged that substantial amounts had been disbursed even though construction had not advanced to the corresponding stages. The project subsequently remained incomplete and the developer entered insolvency proceedings.
The case highlights a recurring financial risk in stalled housing developments: a buyer may be left without possession while still facing demands connected to a loan used to finance the purchase. The buyers in this case said they had continued paying equated monthly instalments and rent, despite not receiving their homes. They also said they had not received the refunds promised during the insolvency process.
The Supreme Court’s direction does not establish that every buyer in an incomplete project can automatically stop repaying a home loan. The report quoted Siddharth Batra, Advocate on Record at the Supreme Court, as saying that delay in completing a project does not by itself entitle a buyer to stop paying instalments that have already fallen due. A buyer’s liability would depend on the financing documents, the builder-buyer agreement and the terms of the tripartite arrangement.
The distinction is important because the court’s intervention concerns the examination of default and the lender’s compliance with the agreed disbursal mechanism. If a bank was required to release funds against construction milestones but paid the developer earlier, a buyer may challenge the amount claimed and the basis on which default has been alleged. However, premature disbursal does not automatically extinguish the underlying loan liability, according to the legal advice cited in the report.
For buyers defending recovery proceedings, the relevant evidence may include the loan sanction letter, tripartite agreement, disbursement statement and the construction-linked payment schedule. Engineer or architect certificates, demand letters, payment receipts and correspondence with the developer can help establish the actual stage of construction and the amounts released. The court’s direction makes the documentary trail particularly significant because the commercial court must first examine the contractual obligations and the alleged mismatch between construction progress and disbursal.
The insolvency proceedings create a separate but connected process. Pranshu G, partner at Ashok Pranshu & Co., advised affected buyers to monitor the public announcement issued in the insolvency case and submit their claims to the interim resolution professional or resolution professional within the prescribed deadline. The claim should set out the principal paid, interest or other amounts claimed and any refund received.
Documents relevant to an insolvency claim include the booking form, allotment letter, builder-buyer agreement, demand notices, payment schedule, receipts, cheque or UTR details and matching bank statements. Where a loan is involved, the sanction letter, tripartite agreement and bank disbursement statement are also important. Buyers should retain proof that the claim was filed and check the resolution professional’s list of creditors, the report said.
For the wider housing market, the order puts the sequencing of lender payments under scrutiny. A construction-linked loan is intended to align financial exposure with the physical progress of a project. When that alignment breaks down, the buyer can face two simultaneous uncertainties: the home may not be delivered, while the financing institution may continue to pursue repayment.
The immediate protection ordered by the Supreme Court is tied to the pending proceedings and the need for the commercial court to determine the buyers’ objections. Its practical significance for other stalled-project buyers will therefore depend on the wording of their agreements, the evidence of construction progress, the lender’s disbursal records and the findings of the court hearing each case.