Officials in Andhra Pradesh’s Alluri Sitarama Raju (ASR) district reviewed mobile connectivity in remote tribal areas and the progress of the NH-516E project on Saturday, with the district administration directing departments to address coverage gaps, land issues and clearance delays.

Joint Collector Tirumani Sripooja held separate video conferences with officials on mobile coverage and the highway project. Representatives of BSNL, BharatNet and engineering departments attended the connectivity review.

The administration assessed network availability across mandals and the connectivity problems reported from interior tribal villages. Officials were asked to provide details of existing coverage, signal-deficient areas, infrastructure requirements and measures needed to improve services.

Sripooja directed BSNL, BharatNet and engineering officials to jointly identify mobile blackspots, collect location-specific data and develop the infrastructure required to bridge coverage gaps. She said improved mobile access was important for government services, emergency response, healthcare, education and digital transactions, and asked officials to prioritise tribal habitations.

The review of the NH-516E project covered construction progress, land acquisition, land disputes, forest clearances and other administrative and technical issues. Revenue officials and tahsildars were directed to expedite pending land acquisition matters, while the Revenue and Forest departments were asked to improve coordination on clearance-related issues.

Project agencies were instructed to monitor construction on the ground, report bottlenecks promptly and accelerate the work. The joint collector described NH-516E as vital infrastructure for the tribal district, saying improved road connectivity would strengthen access to essential services, support tourism and contribute to regional development.

Officials and tahsildars from Dumbriguda, G. Madugula, G.K. Veedhi and Araku Valley attended the project review. The administration directed departments to resolve pending issues within stipulated timelines, but the report did not provide a revised completion schedule, construction percentage or details of the identified mobile blackspots.