MahaRERA Orders Goyal Ganga to Hand Over Bavdhan Duplexes

Maharashtra’s real estate regulator has directed Goyal Ganga Developments LLP to obtain the required approvals and hand over two duplex flats in Pune’s Bavdhan area within 60 days, according to a report on an order dated 17 November 2026. The authority also ordered the developer to pay interest for the delay and ₹20,000 towards the homebuyer’s claim costs.

The case concerns flats 801 and 901 on the eighth and ninth floors of the E-1 building in the Ganga Utopia project. The buyer, Kshitij Bhayyasaheb Godbole, had registered an agreement for the homes on 15 February 2021, with possession scheduled for 30 June 2024.

According to the report, Godbole paid ₹1.32 crore towards the flat price, including GST. With stamp duty, registration fees, legal expenses and tax deducted at source, his total payment was ₹1.39 crore, or about 94.35% of the agreed consideration.

The reported order said the developer had not obtained a revised sanctioned plan and occupancy certificate for the two duplex units after the possession deadline had passed. Pune Municipal Corporation had issued a partial occupancy certificate for other flats in the E-1 building on 9 April 2025, but the two disputed duplexes were excluded, the report said.

Goyal Ganga reportedly argued that the original sanctioned plan provided for two separate flats and that the duplex configuration required revised approval from the municipal corporation. The developer also attributed the delay to a dispute with the original landowner, Marvel Omega Builders Private Limited, over additional floor space index, transferable development rights and documents required for revised approvals.

Other reasons cited by the developer reportedly included arbitration, insolvency proceedings before the National Company Law Tribunal, the appointment of an interim resolution professional and disruptions caused by the Covid-19 pandemic. The developer also argued that the pandemic-related extension recognised by MahaRERA moved the possession date to 30 June 2025.

MahaRERA member Ravindra Deshpande rejected those grounds, as reported. The authority held that disputes arising from the developer’s agreement with the landowner were internal matters and could not curtail the homebuyer’s statutory rights. The regulator also rejected the pandemic defence, noting that the buyer’s agreement was signed on 15 February 2021, after the pandemic had begun, while possession had been promised by 30 June 2024.

The order further distinguished between physical completion and lawful possession. The developer had reportedly maintained that the duplexes were ready for occupation and that only revised approvals and the occupancy certificate remained pending. MahaRERA held that construction completion alone did not amount to legal possession. It directed the developer to first obtain the occupancy certificate and then provide peaceful and lawful possession within 60 days after the buyer paid any legally outstanding amount.

Under the reported directions, interest is payable from 1 July 2024 until the date of actual possession with the necessary approvals. The rate is the State Bank of India’s highest marginal cost of lending rate plus 2 percentage points, calculated on the amount actually paid towards the flat price. Stamp duty, registration charges, GST and other government taxes are excluded from the interest calculation.

The regulator directed the developer to pay interest accrued up to the order date within 60 days and to continue paying interest until lawful possession is delivered. The parties may adjust the interest against any remaining amount payable by the buyer, according to the report.

MahaRERA did not grant Godbole’s separate claim for ₹5 lakh in compensation for mental distress, holding that interest under Section 18 of the Real Estate (Regulation and Development) Act served as compensation for the delay. It did, however, award ₹20,000 in claim costs because the buyer had to approach the authority to enforce his statutory rights.

The order places responsibility for securing project approvals on the promoter after the developer has marketed the configuration, entered into a registered agreement and collected most of the consideration. It also reinforces that a home cannot be treated as legally ready for handover merely because construction is substantially complete when the required municipal approvals and occupancy certificate remain pending.