Maliya Miyana railway bridges aim to keep monsoon trains moving

The Western Railway’s Ahmedabad division has completed three new railway bridges and additional drainage works in the Maliya Miyana area of Morbi district, Gujarat, to reduce the risk of monsoon flooding disrupting passenger and freight services to Kutch and Saurashtra, according to a report by Gujarat Samachar.

The works were carried out on the Viramgam–Samakhiali rail section between Maliya Miyana and Vadharva. Three new water-drainage structures were constructed at bridge numbers 147/D, 147/E and 147/F between kilometre points 699/16 and 699/24. The railway completed the work during a single traffic block using three cranes, each with a capacity of 500 tonnes and a combined capacity of 1,500 tonnes.

Two further drainage structures were built near level crossings 95 and 97, taking the total number of new drainage openings in the section to five. The measures are intended to allow floodwater to pass below the tracks rather than flow across them, reducing the risk of soil erosion beneath the railway formation.

The Ahmedabad division also constructed a 3.7-kilometre protection wall and 12 new culverts to safeguard a vulnerable rail stretch of about seven kilometres. The report said the Maliya Miyana area is prone to water accumulation during heavy rainfall in Saurashtra and when water is released from the Machhu-2 and Machhu-3 dams.

Flooding in 1979, 2017 and August 2024 had washed away soil beneath tracks on the Samakhiali–Maliya Miyana, Dhrangadhra and Wankaner sections, disrupting train operations, the report said. The route is also important for freight because it connects Kandla and Mundra ports with other parts of the country.

The railway has additionally kept reserves of quarry dust, boulders and ballast to respond to monsoon emergencies. The report did not provide the project cost or a detailed maintenance schedule for the new structures.

The divisional railway manager said the objective was not only to repair flood damage but to develop stronger rail infrastructure capable of keeping passenger and freight operations safe and reliable during adverse weather.