HomeAnalysisEjipura flyover faces another delay after nine years of work

Ejipura flyover faces another delay after nine years of work

Bengaluru’s Ejipura flyover is facing another likely delay, with the 2.5-km elevated corridor possibly not ready by the latest December-end target, according to a Times of India report. The unfinished project runs along the busy Koramangala–Ejipura–Madiwala stretch, where commuters have been waiting for relief since construction began in 2017.

The flyover was originally scheduled for completion in November 2019. Since then, its targets have moved through 2020, December 2021, 2025 and several dates in 2026. The latest delay leaves pending work on ramps, pavement, crash barriers, drainage, lighting, lane markings and road signage. Additional entry and exit ramps towards Sarjapur Road also require further land acquisition.

The project was awarded to Kolkata-based Simplex Infrastructure Ltd in 2017 at an estimated cost of Rs 158 crore. BBMP issued the work order on May 4 that year. Progress was affected by delays in traffic police clearances, permission for controlled blasting and the acquisition of land needed for construction.

By 2020, BBMP was still working to acquire portions of land belonging to St John’s Hospital, the Central Public Works Department and the Indian Institute of Astrophysics. The Covid-19 pandemic further disrupted labour mobilisation. Simplex, which was facing financial difficulties, ultimately failed to complete the work.

A public interest litigation filed in 2021 brought the project before the Karnataka High Court. BBMP terminated Simplex’s contract in March 2022, after spending around Rs 75 crore on the project, the report said. The civic body also forfeited the contractor’s security deposit of Rs 10.16 crore and imposed a penalty of about Rs 2.5 crore.

Replacing the contractor added another layer of delay. BBMP floated a fresh tender in August 2022, but recalled it. A January 2023 tender valued at Rs 144 crore attracted a single bid from Hyderabad-based BSCPL Infrastructure Ltd. The company quoted about Rs 205 crore, approximately 44% above the estimate, and the bid did not receive financial approval. BBMP cancelled the tender in February 2023.

After revising the estimates and adding a price-adjustment clause, BBMP awarded the remaining work to BSCPL in November 2023. The contractor received a 15-month completion deadline, while the cost of the remaining construction was pegged at Rs 176.1 crore, excluding GST.

The change in contractor did not immediately resolve the project’s problems. BSCPL cited delays in land acquisition, mobilisation payments and access to a casting yard. It also required an assessment by the Indian Institute of Science of the structure built by Simplex before continuing construction. That assessment was completed in May 2024, several months after BSCPL took over. BBMP later issued notices to BSCPL over slow progress and imposed a penalty of Rs 25 lakh.

Construction activity picked up in 2025, but land acquisition near St John’s Medical College Hospital continued to affect the ramps. In January 2026, GBA chief commissioner M Maheshwar Rao directed officials to mark the land required at the hospital and begin work on five portal piers. Hospital management agreed to the temporary use of a portion of land along the compound wall, with instructions to install barricades and rebuild the wall after construction.

The project has also faced objections over BBMP’s proposal to remove 157 trees along Koramangala’s 100 Feet Road. More than 150 objections and suggestions were received before the public-submission deadline in January 2025. Residents proposed changes to the ramp design and alignment to protect trees, while activists questioned changes in the number of trees proposed for removal.

The Ejipura flyover’s prolonged construction illustrates how an urban transport project can be delayed by a chain of linked decisions rather than a single unresolved issue. Contractor failure led to termination and retendering; retendering was affected by bid pricing and financial approval; the replacement contractor faced land, payment and access constraints; and later construction remained tied to structural assessment, ramp design and environmental objections.

For commuters, the immediate issue is the continued absence of a functioning elevated corridor on the Koramangala–Ejipura–Madiwala route. The project’s remaining work also means that the latest target does not represent a guaranteed opening date. The report indicates that both the main corridor and the Sarjapur Road ramps still have unfinished elements, leaving the timing of full completion uncertain.