Construction of the 3.39-km IIIT Junction multi-level interchange at Gachibowli has accelerated after the monsoon, with 43 of its 54 foundational pillars completed, Telangana Today reported on November 18.
Cyberabad Municipal Corporation (CMC) officials said structural concrete beam installation was under way for three interconnected steel flyover stretches at the junction. The project is being developed under the Hyderabad City and Innovative Transformative (H-CITI) programme to address congestion in Hyderabad’s IT corridor.
The planned signal-free network will include three elevated steel flyovers and a six-lane underpass. Its Level-1 bi-directional flyover will be a 720-metre, four-lane link between ISB Road and DLF Road, carrying traffic in both directions.
Two upper-level flyovers will connect ISB Road to Gachibowli and DLF Road to Lingampally. The first will extend for 1.20 km, while the second will cover 948 metres. The design uses shared double-decker pier systems and dual-load edge pillars at selected locations, according to the report.
Another Level-2 structure will provide a 1.2-km, three-lane elevated route for vehicles travelling from ISB Road towards Gachibowli and Indira Nagar. It will use prefabricated structural steel girders and carry right-turning traffic above the lower Level-1 flyover, allowing those movements to avoid signal stops.
The DLF Road–Lingampally flyover will also support movement towards Lingampally and Gachibowli Stadium. The multi-level arrangement is intended to reduce land acquisition requirements and overall costs, CMC officials said.
CMC officials told Telangana Today that the H-CITI project is targeted for completion by May 2027. They estimated that the completed interchange could reduce peak-hour travel times by 10 to 15 minutes for nearly 400,000 to 500,000 daily commuters travelling between HITEC City, the Financial District, Kokapet and Lingampally.
The project is also expected, according to the officials, to improve access to DLF, ISB, the Financial District and the Outer Ring Road. The reported construction progress concerns the interchange’s foundations and structural works; the report did not provide a revised completion schedule beyond the May 2027 target.