Jakkur Railway Overbridge Finally Opens After 15-Year Delay

The Jakkur railway overbridge in north Bengaluru is set for formal inauguration by Chief Minister D K Shivakumar on Wednesday, ending a nearly 15-year wait for a project intended to remove a major level-crossing bottleneck between Jakkur, Yelahanka and surrounding areas. The 443-metre, four-lane bridge has already been open to traffic for more than a month, according to the report, but its official inauguration had been pending.

Located on Jakkur Main Road, the overbridge allows vehicles to bypass the railway-level crossing near Yelahanka Raitha Santhe and travel towards Airport Road. Bengaluru North City Corporation (BNCC) said the facility is expected to reduce travel distance by around 3 km and save motorists approximately 15 minutes on routes towards Yelahanka, Hebbal, Thanisandra, Kogilu and Ballari Road.

The project cost Rs 69.6 crore, including construction and land acquisition. Construction accounted for nearly Rs 26.2 crore, of which South Western Railway contributed Rs 6.4 crore and the erstwhile Bruhat Bengaluru Mahanagara Palike (BBMP) contributed Rs 19.8 crore. BBMP bore the full land acquisition cost of Rs 43.5 crore.

South Western Railway initiated the project in 2011, but construction stopped in 2014 because of difficulties in acquiring the land needed for the bridge. BBMP resumed the acquisition process in 2017 under a direct purchase scheme. Of the 48 properties required, 33 were acquired at a cost of Rs 25 crore.

Construction was discontinued again by SWR in 2018, leaving five spans of girders in place while the reinforced cement concrete obligatory span remained incomplete. In 2024, BBMP issued a fresh work order for the remaining construction with a stipulated completion period of 10 months. The work nevertheless faced additional delays because land acquisition was still incomplete.

Six more properties were subsequently acquired, with Rs 18.5 crore paid as compensation. A further Rs 15 crore was sanctioned for the remaining construction, which was eventually taken up and completed by BNCC. The project’s administrative responsibility therefore moved from SWR to BBMP and finally to the city corporation responsible for Bengaluru North.

The inauguration will also include the foundation stone ceremony for a separate Rs 436.5-crore elevated rotary flyover at IOC Junction and an additional two-lane railway overbridge near the Byappanahalli railway level crossing. The project is being executed by Bengaluru Smart Infrastructure Ltd under the state government’s special infrastructure capital scheme and has a stipulated completion period of 24 months.

The proposed flyover will have a four-lane carriageway and ramps connecting it with Banaswadi Road, Kammanahalli, Old Madras Road through Sir M Visvesvaraya Terminal and Maruthi Sevanagar Road. According to the project details, it is intended to ease congestion at IOC Junction and the nearby railway crossing, improve access to the terminal, reduce travel time and curb vehicular pollution. The foundation stone ceremony and the Jakkur overbridge inauguration are scheduled for Wednesday.