HomeBreaking NewsTarali Pumped Storage Project Halted Over Wildlife Clearance Gap

Tarali Pumped Storage Project Halted Over Wildlife Clearance Gap

Work on the 1,500MW Tarali pumped storage project in Maharashtra’s Satara district has been ordered to stop after the deputy conservator of forests (DCF), Satara forest division, said the project had commenced without prior approval from the National Board for Wildlife (NBWL).

The order was issued to the project manager of Adani Renewable Energy One Ltd, Mumbai, by DCF Amol Satpute. The project is being executed by Adani Green Energy Ltd (AGEL) in Patan taluka. The forest department has warned that continued work could invite strict legal and penal action under applicable forest laws.

The action follows a show-cause notice issued on November 13 under the Wildlife (Protection) Act, 1972, and the Maharashtra Tree Felling (Regulation) Act, 1964. The notice sought an explanation for the authority under which the project was initiated without valid NBWL permission and asked the company to submit its response within three days of receiving it.

The forest department has also sought details of permissions for tree felling linked to the project, including the total number of trees approved for felling and original or attested copies of permits, if such permissions exist. The company has been asked to provide all related statutory approvals and project maps.

AGEL said the project had received the necessary permissions and no-objection certificates for land use and other statutory requirements. An AGEL spokesperson said the environmental clearance was granted in February 2025 and that the Maharashtra Pollution Control Board issued consent to establish on April 7, 2025, allowing work to begin.

“Construction activities commenced only after obtaining all the requisite approvals from the authorities concerned,” the spokesperson said. The company added that its wildlife-clearance process had been initiated and that a proposal for survey and investigation activities was submitted in January 2025. According to AGEL, the proposal was subsequently recommended by the state board for wildlife and has since been submitted to the NBWL, where it is under consideration.

The company also said that no component of the project falls within a notified protected area or forest land, and that it received a related no-objection certificate on January 23, 2024. The forest department’s order, however, specifically questions whether the project had the required wildlife approval before work began.

The stop-work action also follows concerns raised in October over the project cost recorded in different submissions. The environmental clearance issued by the Ministry of Environment, Forest and Climate Change on February 11, 2025, records the project cost as Rs 5,675 crore. It lists Rs 39.3 crore as capital expenditure for the environment management plan and pollution-control measures, along with Rs 27.5 crore in recurring operation and maintenance costs.

Separately, a September 7 undertaking submitted by AGEL chief operating officer Naresh Telugu reportedly cited the project cost as Rs 56.75 crore. AGEL has said that this figure related only to preliminary investigations and surveys and denied allegations that the project cost was understated to reduce statutory obligations.

Satara honorary wildlife warden Rohan Bhate had sought an inquiry into the difference between the two figures and its potential effect on wildlife conservation contributions. He cited an estimated requirement equivalent to 4% of the project cost for the Sahyadri Tiger Reserve Conservation Foundation, which would amount to approximately Rs 227 crore on the higher figure. Based on the lower figure, 1% was calculated as Rs 56.75 lakh, with the remaining 3% to be paid after NBWL clearance, according to his representations.

The immediate next step is the company’s response to the forest department’s notice, along with the requested approvals, tree-felling permissions and project documents. Work at the site remains subject to the directions issued by the Satara forest division.