Sabarmati Riverfront Phase 2 Reaches 83%, Bridge Due by 2027

Sabarmati Riverfront Phase 2 in Ahmedabad has reached a reported 83% overall completion, with the ₹1,285-crore expansion targeted for completion by December 2027, according to details reviewed during Gujarat Chief Minister Bhupendra Patel’s inspection of the project works on November 16.

The second phase covers a 5.5-kilometre stretch of the Sabarmati. Since development is taking place on both banks, the project encompasses 11 kilometres of riverfront. It includes river walls, stepped embankments, access routes, promenades, roads, green zones and public amenities on the northern section of the riverfront.

The Chief Minister inspected the six-lane barrage-cum-bridge being built between Acher on the western bank and Camp Sadar Bazar on the eastern bank. The 1,048-metre bridge is reported to be 37% complete and is expected to be finished by December 2027. The project has an estimated cost of ₹239.42 crore.

The barrage-cum-bridge will be operated through an automatic control system and will include a 3.5-metre-high specialised rubber-type barrage. Officials said the structure is intended to help maintain water storage in the riverfront area towards Gandhinagar. The project has also been described as the first of its type in Gujarat.

Other locations reviewed during the inspection included the canopy structure at Sardar Patel Enclave, works behind the Koteshwar Mahadev Temple and construction under the Indira Bridge. The Chief Minister also reviewed progress in areas covered by Phase 3, including the western bank opposite Koteshwar and the Narmada Canal escape near Karai.

The project’s river wall, stepped embankment, access and middle promenade works are reported to be 93% complete. These components have an estimated cost of ₹399.37 crore and are targeted for completion by February 2027. By contrast, infrastructure works connected to roads and other facilities on both banks are reported to be 15% complete. These works have an estimated cost of ₹180 crore and are scheduled for completion by December 2027.

Phase 2 is planned to include green zones, planting at different levels, children’s play areas, food plazas, spaces for art and culture, and seating for visitors. The expansion is therefore combining river-edge engineering with public-realm facilities, while the bridge and barrage are intended to add a new cross-river connection and support water retention.

Phase 3 is planned to extend the riverfront from Indira Bridge to the Narmada Main Canal. That section covers a five-kilometre river stretch, or 10 kilometres across both banks. Once Phases 2 and 3 are completed, the Sabarmati Riverfront will have a substantially larger developed footprint. During the review, the Chief Minister directed officials to accelerate the remaining works.