HomeBreaking NewsPaharganj Building Collapse: Owner, Contractor Arrested After 8 Hurt

Paharganj Building Collapse: Owner, Contractor Arrested After 8 Hurt

Delhi Police have arrested a property owner and a contractor after a building construction accident in central Delhi’s Paharganj injured workers, triggering a criminal case over alleged negligent conduct during construction.

The incident occurred on Sunday evening in the Sangaratan area of Paharganj when a newly constructed lintel or roof section collapsed while workers were removing temporary shuttering. Police said eight people were taken to Lady Hardinge Medical College and Hospital for medico-legal examination. Their condition was reported to be stable.

The arrested individuals were identified as the property owner, Raman, and the contractor, Anwar. Police registered a first information report at Paharganj police station under Sections 290 and 125(a) of the Bharatiya Nyaya Sanhita. Section 290 concerns negligent conduct during the repair or construction of a building, while Section 125(a) deals with endangering life through a rash or negligent act.

The Delhi Fire Service received information about the collapse at 4.40 pm. Firefighters, police personnel and local residents helped evacuate the injured and take them to hospital. The police said further investigation into the circumstances of the accident was under way.

The construction was taking place opposite a government girls’ school. According to the police account, workers were removing lintel shuttering on the second floor when the collapse occurred. A report prepared by the Municipal Corporation of Delhi, however, described the incident as taking place while shuttering was being removed at ground level, with a section of a newly built lintel suddenly giving way. The supplied reports therefore differ on the precise level at which the collapse occurred.

The MCD report also recorded five people as having suffered minor injuries, while the police said eight people were taken to hospital for medico-legal examination. The difference may reflect separate stages or methods of recording the casualties, but the authorities had not provided a consolidated count in the reported material.

The civic report said the building was being constructed under an approved building plan issued on June 4, 2024. It also said that inspectors found no unauthorised construction at the property during their inspection. By that stage, construction of the basement, the ground-floor parking area and part of the floor above it had been completed.

The MCD did not specify the precise technical reason for the collapse. It said officials were examining the circumstances surrounding the accident. The police case will now determine whether the owner, contractor or other parties failed to follow required safety practices during the removal of temporary construction supports.

The incident places attention on the safety risks associated with temporary shuttering and lintel work in dense urban neighbourhoods, where construction sites can be close to homes, schools and public movement. The next steps are the continuing police investigation and the authorities’ examination of the construction sequence and site conditions.