The proposed Pune ropeway linking Peshwe Park with Parvati has moved to its next planning stage after the Pune Municipal Corporation standing committee approved the appointment of a management consultant for the project on November 1, according to Lokmat – Pune. The consultant will assess the site, prepare the detailed project report (DPR), estimate costs and frame the conditions for the tender process.
Standing committee chairperson Shrinath Bhimale said the ropeway has been proposed to promote tourism in the city. The project has received a provision of Rs 1 crore in the Pune Municipal Corporation’s 2026-27 budget, although the final project cost will be determined through the technical and financial assessment.
The civic body plans to assign the consultant responsibility from the initial planning stage through the tendering process. This will include preparing the detailed project design, examining the project’s technical and financial feasibility, and conducting the process required to appoint an implementing agency.
The ropeway is expected to use electrical and mechanical systems. The municipal corporation currently does not have the specialist manpower required to plan and develop such a project, making the proposed consultant’s role central to determining whether the concept can proceed and under what implementation model.
The consultant will also inspect the proposed project site and prepare the DPR, cost estimate and tender terms and conditions. The consultancy will identify the government permissions needed for the project and establish the process for obtaining them. These approvals will be required before construction can move ahead.
The civic body will also examine whether the project is financially viable under a public-private partnership model or through the Design-Build-Finance-Operate-Transfer, or DBFOT, model. The approval therefore begins a feasibility and procurement exercise rather than confirming a construction start date or final funding structure.
The proposed ropeway route is around 750 metres long and is planned to run from Peshwe Park to Parvati. The preliminary plan includes five towers, with heights ranging from 12 metres to 40 metres, and 22 cabins. Each cabin is expected to carry eight passengers, with a proposed journey time of two and a half minutes.
The planned system is designed to carry up to 1,500 passengers per hour in one direction. The figures are part of the proposed project parameters and may be reviewed during the consultant’s site assessment, DPR preparation and feasibility study. The next formal steps are the appointment of the consultant and the preparation of the technical, financial, regulatory and tender documents.