Ahmedabad Road Repairs Get 48-Hour Deadline Under New SOP

Ahmedabad road repairs will now be governed by mandatory inspections before and after the monsoon, with dangerous roads required to be repaired within 48 hours under a new standard operating procedure issued by the Gujarat government for municipal corporations across the state.

The Ahmedabad Municipal Commissioner has instructed the civic body’s engineering department to implement the SOP, which focuses on road construction quality, timely maintenance and the safety of pedestrians, cyclists, persons with disabilities and other road users.

Under the new process, all roads must be surveyed before and after the monsoon. Small patchwork repairs will have to be completed within 30 days, while damaged concrete road surfaces must be repaired within 15 days. Roads considered seriously damaged and dangerous for citizens will require repairs within 48 hours.

The SOP also requires municipal teams to upload photographs of completed repairs to the corporation’s application within 72 hours. Barricading will be compulsory during repair work. Before filling a pothole, the surface must be cleaned and treated with suitable bitumen emulsion. The guidelines also mention cold emulsion injection and infrared recycling as possible repair technologies.

The instructions set out additional quality controls for hot-mix road construction. Contractors and project management consultants must submit a quality assurance plan before work begins, and construction can start only after approval from the competent authority. The source, quality and available quantity of raw materials must be checked, while quality personnel must be present at both the hot-mix plant and the work site.

Records must be maintained for the weight of material leaving the plant, its dispatch time, arrival time at the site and temperature. Material that does not meet prescribed quality standards cannot be sent to the site or reused. Before hot mix is laid, the surface must be cleaned, the material spread at the correct temperature and approved thickness, and the road level and gradient maintained.

Laboratory testing will also be required, with precautions to prevent damage to manholes, valve chambers and catch pits. Road registers must be maintained and updated every October. For resurfacing, regrading or milling work, relevant officials and design consultants must jointly inspect the site.

Road estimates will have to include details of water lines, drainage, stormwater lines and other underground utilities. Repeatedly failing drainage or stormwater lines, along with manholes, will need to be rehabilitated or strengthened before new road construction begins. Officials must record the existing road surface, the thickness of underlying layers and the level near building entrances.

The SOP also identifies locations requiring special design attention, including areas with weak soil, black cotton soil, high groundwater levels and recurring waterlogging. Industrial roads carrying heavy vehicles, BRTS corridors, accident-prone roads and stretches that repeatedly require costly repairs may be considered for RCC construction.

The new requirements place repair deadlines alongside construction-stage checks, but their implementation will depend on regular surveys, accurate underground utility records, contractor compliance and timely municipal monitoring. The Ahmedabad Municipal Corporation’s engineering department is expected to begin implementation under the Commissioner’s direction.