A three-hour power outage affected residents around Gopinath Chowk in Dombivli West on Wednesday after an underground electricity cable was damaged during road excavation for a Mumbai Metropolitan Region Development Authority (MMRDA) project. The supply was restored after Maharashtra State Electricity Distribution Company Limited (MSEDCL) teams repaired the damaged line.
The incident occurred at about 11 am while an MMRDA contractor was carrying out excavation near Gopinath Chowk. The work forms part of the first phase of widening and concreting a 40-foot road between Gopinath Chowk and the Jagdamba Mata Temple area in Dombivli West.
According to the report, the contractor was using a JCB machine to excavate the roadside section while preparing the road base. The underground cable supplied electricity towards Laxmi Narayan Krupa Society and nearby areas. It was damaged during the excavation, causing the local power supply to fail suddenly.
The outage continued from 11 am until 2 pm, affecting residents and other consumers in the Gopinath area. The report did not specify the number of connections affected, but said citizens faced difficulties during the three-hour interruption.
MSEDCL officials were informed after the cable was damaged. Nitin Satkar, assistant engineer in the utility’s Retibunder area, sent a repair team to the site to restore the line. Since the damaged cable was underground and difficult to access, MSEDCL employees carried out the repair and jointing work before supply was restored.
The road project is being executed in stages. The first phase involves work between Gopinath Chowk and the Jagdamba Mata Temple area, including preparation of the road’s sub-base with aggregate and a roller before concrete work. The excavation was being undertaken along the road edge as part of this preparation.
The incident has also drawn attention to the disruption caused when underground utility lines are damaged during road and infrastructure works. The Loksatta report said MMRDA works in different parts of the city have resulted in underground electricity cables being damaged by excavation machinery, increasing the workload for MSEDCL officials and repair staff. It also reported that MSEDCL employees had faced additional difficulties while attending to such incidents during the monsoon.
The outage was resolved after the MSEDCL repair team completed the underground cable work. Further details on the project’s next construction stage and any revised excavation or utility-coordination measures were not provided in the report.