HomeLatestMumbai Airoli–Kalwa Rail Work Stuck Due To Land, Rehab Problems

Mumbai Airoli–Kalwa Rail Work Stuck Due To Land, Rehab Problems

Mumbai’s long-awaited Airoli–Kalwa elevated suburban rail corridor, designed to relieve congestion at Thane railway station and bolster connectivity across the metropolis, has hit its most significant roadblocks yet—land disputes and rehabilitation delays. The Mumbai Railway Vikas Corporation (MRVC) reports 45% of the project is complete, but the remaining tasks centre squarely on overcoming social and acquisition challenges.

Despite the MRVC securing over 95% of the 2.40 hectares needed, the acquisition of 0.53 hectares of private land and resettlement of 786 affected families in Bhola Nagar and Shivaji Nagar remain unresolved. A senior MRVC official asserted that ongoing engagement with state authorities is “actively addressing” the hold-ups. The corridor, launched eight years ago, is split into two actionable phases. The first phase—entailing a new halt at Digha Gaon and substantial bridge and underbridge work—was commissioned in January 2024 and advanced without land acquisition complications. However, the elevated second phase connecting Airoli and Kalwa has stalled, pending rehabilitation of the displaced.

While 1.87 hectares of government land was acquired smoothly, the private parcels and intensive R&R processes have faced resistance from local residents. MRVC and Mumbai Metropolitan Region Development Authority (MMRDA) are reportedly convening regular sessions with households and officials to reach a resolution. However, no concrete timeline has yet been confirmed. MRVC emphasises a completion timeline—36 months after finalising R&R—and maintains that authorities from the Ministry of Railways and Maharashtra Government are advocating for “sustainable, inclusive, commuter-centric” implementation. Once operational, the corridor promises to reduce pressure on Thane station and enhance rail access for commuters in zones like Mumbra, Diva, Dombivli and Kalyan.

Also Watch: “Mumbai will rock, shine and always be India’s best city to live.” In an exclusive, MHADA CEO Sanjeev Jaiswal (IAS) talks about Mumbai’s enduring charm, livability, and the government’s focus on making it affordable for all

Transport specialists highlight the project’s broader implications. By reinforcing suburban infrastructure and alleviating passenger loads, the corridor supports Mumbai’s low-carbon vision and equitable transport network. “Faster elevated rail reduces road traffic, boosts efficiency and cuts carbon emissions. But successful implementation relies on timely R&R,” said a transit planning expert. Critics, however, urge more proactive engagement with affected residents to ensure transparency and alleviate mistrust. “Public infrastructure projects achieve success when social inclusion matches engineering ambition,” noted a social policy analyst. Failure to address rehabilitation adequately could strain civic relationships and prompt costly delays.

With nearly half the corridor completed, its potential is clear—but unlocking its benefits depends on navigating land rights and rehabilitative justice. As Mumbai confronts rapid urban growth, this elevated rail link stands at the crossroads of engineering prowess and community-sensitive policymaking. The MRVC remains resolute: once resettlement is secured, physical completion will follow. Meanwhile, its success may well shape future transit projects and inform equitable infrastructure models in emerging megacities.

Also Read : Two Delhi-IndiGo flights faced mid-air issues; one returned, another diverted to Mumbai

Mumbai Airoli–Kalwa Rail Work Stuck Due To Land, Rehab Problems
RELATED ARTICLES
- Advertisment -spot_img

Most Popular

Latest News

Recent Comments